Link to PDF file
655 S.E.2d 494
IN THE SUPREME COURT OF APPEALS OF WEST VIRGINIA
September 2007 Term
___________
No. 33286
___________
PREUSSAG INTERNATIONAL STEEL CORPORATION,
dba INFRA-METALS CO.,
Plaintiff
v.
MARCH-WESTIN CO.; TITAN FABRICATION &
CONSTRUCTION CO.; ZURICH AMERICAN
INSURANCE CO.; and FIDELITY DEPOSIT CO.
OF MARYLAND,
Defendants
_____________________________________________________
UNITED STATES DISTRICT COURT FOR THE
NORTHERN DISTRICT OF WEST VIRGINIA
Hon. Irene M. Keeley, Judge
Case No. 1:04-CV-233
CERTIFIED QUESTION ANSWERED
AND OPINION CERTIFIED TO THE
UNITED STATES DISTRICT COURT FOR THE
NORTHERN DISTRICT OF WEST VIRGINIA
________________________________________________________
Submitted: September 12, 2007
Filed: November 9, 2007
James F. Companion, Esq.
William H. Hutchens, III, Esq.
John Porco, Esq.
Jackson Kelly, PLLC
Schrader, Byrd & Companion, PLLC
Morgantown, West Virginia
Wheeling West Virginia
Attorney for March-Westin Co.,
William K. Kane, Esq.
Inc.
Erin Bolan Hines, Esq.Lovells Carl L. Fletcher, Jr., Esq.
Chicago, Illinois
Daniels Law Firm, PLLC
Attorneys for Plaintiff
Charleston, West Virginia
Attorney for Amicus Curiae
Rochelle R. Koerbel, Esq.
Contractors Association of
Blumling & Gusky, LLP
West Virginia
Pittsburgh, Pennsylvania
Attorney for Amicus Curiae The Surety
& Fidelity Association of America
JUSTICE STARCHER delivered the Opinion of the Court.
SYLLABUS BY THE COURT
1. Necessary material furnished for, or necessary labor performed on, a
public structure under a contract with the general contractor or subcontractor, is protected by
the bond required by Code, 38-2-39. Material supplied to, or labor performed for, a furnisher
of material on a public structure is not so protected. Syllabus Point 1,
Marsh v. Rothey, 117
W.Va. 94, 183 S.E. 914 (1936).
2. A subcontractor, ordinarily, is one to whom the principal contractor
sublets a portion or even all of the contract itself. A materialman, ordinarily, is one from
whom the principal contractor or a subcontractor secures material of a general type for use
on the structure. Syllabus Point 2, Marsh v. Rothey, 117 W.Va. 94, 183 S.E. 914 (1936).
3. For purposes of the public construction bond statute, W.Va. Code, 38-2-
39 [2004], a party need not necessarily perform work at the construction job site itself in
order to be considered a subcontractor. To make the determination in a public construction
bond case whether a party that furnishes labor or materials to the project should be classified
as a subcontractor or as a materialman, a multi-factorial analysis should be used, with no
single factor being determinative. The core inquiry is whether the party in question takes
from the prime contractor a specific and substantial part of the labor or material requirements
of the original contract, thus excluding ordinary laborers and materialmen.
Starcher, J.:
In the instant case we hold that a bond posted to guarantee the payment of those
who provide labor and materials for a public building construction project is available to pay
a company that provided the raw steel used by another company to custom-fabricate the steel
structure of the building.
I.
Facts & Background
Pursuant to
W.Va. Code, 51-1A-3 [1996] (the Uniform Certification of
Questions of Law Act), the United States District Court for the Northern District of West
Virginia has certified a question of law to the Supreme Court of Appeals of West Virginia.
We quote from the District Court's order framing the question:
I. THE QUESTION OF LAW TO BE ANSWERED
Under
W.Va. Code, 38-2-39 (2004), is a steel fabricator
deemed to be a subcontractor where:
A. The steel fabricator enters a fixed-price contract
with the general contractor of a public works construction
project, pursuant to which the fabricator
i. Agrees to fabricate and deliver structural steel
components conforming to the construction project's unique
design specifications;
ii. Produces shop drawings for the fabricated steel
components based on the project's engineering calculations and
design specifications;
iii. Submits its shop drawings for approval by the
project's architect and general contractor before fabricating the
structural steel components; and
iv. Delivers the fabricated steel components on a
delivery schedule based on construction progress;
B. The steel fabricator performs all physical
fabrication processes at its own facility, away from the project
site; AND
C. The fabricated steel components are not fungible
and not readily marketable without further modification?
The District Court's order also included the following Statement of Facts: (See footnote 1)
On August 25, 2003, Fairmont State College (FSC) retained
March-Westin Co. (March) as general contractor to construct
a new Student Recreation Center at FSC (the Project). The
contracted price for the completed Project was $20,210,140. In
accordance with W.Va. Code, 38-2-39, March obtained a surety
Bond through two private surety companies, Zurich American
Insurance Co. and Fidelity Deposit Co. of Maryland (the
Sureties). Subsequently, on September 19, 2003, March and
Titan Fabrication & Construction Co. (Titan) entered into a
fixed price contract,1 wherein Titan agreed to fabricate and
deliver $1,204,584 worth of specially fabricated structural steel
components required for the Project. In performing its scope
of work,2 Titan purchased non-fabricated steel from numerous
materialmen, including Preussag International Steel Corp., dba
Infra-Metals Co. (Infra), the plaintiff in the present
controversy. In pertinent part, the record before the court shows
that:
A. Titan performed all fabrication at a facility away from the
Project site;3
B. Titan's material suppliers, including Infra, provided Titan
with non-fabricated steel of a general nature;
C. In accordance with the Project's design specifications,
Titan worked the raw steel into specially fabricated structural
steel components;
D. The specially fabricated steel components were not
readily marketable without further modification; E. Titan's invoices to March separately accounted for
various aspects of its scope of work, showing costs of materials
supplied by each of Titan's materialmen, including Infra.
F. Titan's inability to deliver the specially fabricated steel
would have effectively shut the project down;
G. Infra allegedly supplied $557,264.97 of non-fabricated
steel to Titan, for use on the Project, for which it was never
paid;4
H. Infra filed for payment under the Bond on June 22, 2004;
I. The Sureties denied payment to Infra, claiming that Titan
was a mere materialman and that Infra is not within the class
of persons protected under Bonds issued pursuant to W.Va.
Code, 38-2-39.
All parties agree that, if Titan is deemed to have been a
subcontractor rather than a materialman, then Infra would be
entitled to payment under the Bond. Given the facts of this case,
both parties agree that whether Titan is a subcontractor or a
materialman presents an unsettled question of West Virginia law
appropriate for certification. The parties also agree that Marsh
v. Rothey, 183 S.E. 914 (W.Va. 1936), is the leading case
construing W.Va. Code, 38-2-39. They also agree, however, that
the facts before the Marsh court were distinguishable from those
now before the court and that the Marsh holding is not
dispositive of the issue at bar. Nonetheless, Infra contends that
the Bond statute, as construed by the Marsh court, mandates that
one who supplies material that is not of a general type, but
instead if worked according to project specifications, is a
subcontractor. By contrast, March and the Sureties assert that
an entity's status as a materialman or subcontractor is
contractually defined, and that, even if such status is not
contractually defined, there is nonetheless a requirement that
one physically perform work at the Project site to be deemed a
subcontractor.
___________________
1[Footnotes to District Court's order] Both the general contract between March
and FSC and the contract between March and Titan were executed on documents
formally entitled Purchase Orders.
2 Record documents authored and provided by March refer to Titan's role in
terms of its scope of work.
3 The record is silent as to whether any of Titan's duties were performed at the
Project site
4 Titan filed for bankruptcy protection in November 2004 and is currently under
a protective stay.
To summarize the facts and central issue of the instant case: March was the
general contractor for a twenty-million-dollar public building. March contracted with Titan
to fabricate and deliver the steel structural elements of the building, at a price of more than
a million dollars. Titan ordered and received raw steel beams, plates, etc. from Infra _ but
Titan did not pay Infra. Infra, which the parties agree was a materialman, now seeks
payment from the bond posted by March. It is settled law (as we discuss further infra) that
if Titan was a subcontractor on the project, Infra has a right to make a claim against the
bond. But If Titan was a mere materialman, Infra cannot make a claim against the bond.
II.
Standard of Review
In Wilson v. Bernet, 218 W.Va. 628, 631, 625 S.E.2d 706, 709 (2005), this
Court said:
The issues presented by the instant matter involve questions of
law certified to this Court. When called upon to consider
certified questions, we employ a plenary review and review
anew the answers provided by the circuit court. The appellate
standard of review of
questions of law answered and certified by
a circuit court is
de novo. Syl. pt. 1,
Gallapoo v. Wal-Mart
Stores, Inc., 197 W.Va. 172, 475 S.E.2d 172 (1996).
See also Syl. pt. 1,
Bower v. Westinghouse Elec. Corp., 206 W.Va. 133,
522 S.E.2d 424 (1999) (This Court undertakes plenary review
of
legal issues presented by certified question from a federal
district or appellate court.); Syl. pt. 1,
Light v. Allstate Ins. Co.,
203 W.Va. 27, 506 S.E.2d 64 (1998) (A de novo standard is
applied by this Court in addressing the
legal issues presented by
a certified question from a federal district or appellate court.).
(Emphasis added.)
(See footnote 2)
III.
Discussion
W.Va. Code, 38-2-39 [2004], states as follows:
It shall be the duty of the state commissioner of public
institutions, and of all county courts, boards of education, boards
of trustees, and other legal bodies having authority to contract
for the erection, construction, improvement, alteration or repair
of any public building or other structure, or any building or
other structure used or to be used for public purposes, to require
of every person to whom it shall award, and with whom it shall
enter into, any contract for the erection, construction,
improvement, alteration or repair of any such public building or
other structure used or to be used for public purposes, that such
contractor shall cause to be executed and delivered to the
secretary of such commissioner or other legal body, or other
proper and designated custodian of the papers and records
thereof, a good, valid, solvent and sufficient bond, in a penal
sum equal at least to the reasonable cost of the materials,
machinery, equipment and labor required for the completion of
such contract, and conditioned that in the event such contractor
shall fail to pay in full for all such materials, machinery,
equipment and labor delivered to him for use in the erection,
construction, improvement, alteration or repair of such public
building or other structure, or building or other structure used or
to be used for public purposes, then such bond and the sureties
thereon shall be responsible to such materialman, furnisher of
machinery or equipment, and furnisher or performer of such
labor, or their assigns, for the full payment of the full value
thereof.
No officer or employee of this state or of any public agency,
public authority, public corporation, or other public entity, and
no person acting or purporting to act on behalf of such officer or
employee or public entity shall require that any surety bond
required or permitted by this section be obtained from any
particular surety company, agent, broker or producer.
All such bonds shall have as surety thereon either some
incorporated bonding and/or surety company authorized to carry
on business in this state, or in lieu of such corporate surety the
contractor may deposit as security for such bond with the said
state commissioner of public institutions, county court, board of
education, board of trustees or other legal body having authority
so to contract, a sum in cash or bonds and securities of the
United States of America or of the state of West Virginia of
sufficient amount and value equal at least to the reasonable cost
of materials, machinery, equipment and labor required for the
completion of such contract. Immediately upon the acceptance
of either of said bonds by the state commissioner of public
institutions, county court, board of education and board of
trustees, or other legal body, the bond shall be recorded by the
secretary of such commissioner or other legal body, or by the
proper designated custodian of the papers or records thereof, in
the office of the clerk of the county court of the county or
counties wherein such work is to be done and where such
materials, machinery or equipment are to be delivered, and no
such contract shall be binding and effective upon either party or
parties thereto until such bond has been executed, delivered and
recorded as aforesaid.
Nothing in this article shall be construed to give a lien upon
such a public building or improvement as is mentioned in this
section, or upon the land upon which such public building or
improvement is situated.
This Court addressed the purpose, application, and construction of W.Va. Code,
38-2-39 [2004] in Cecil I. Walker Machinery Co. v. Stauben, Inc., 159 W.Va. 563, 567-70,
230 S.E.2d 818, 820-21 (1976):
Liens against public projects have not been permitted. As a
consequence, those who would be protected by mechanic's liens
or materialmen's liens if the project were a private project have
found their protection in statutes requiring bonds for their
protection.
***
It has been uniformly held that a bond given pursuant to a
statute should be read as though given in literal compliance with
the statute. Likewise, when the surety is a corporation and
supplies bonds for a consideration, the courts will construe the
obligations of the bond most strongly against the surety.
[citations omitted.]
***
Generally speaking, the courts have endeavored to extend the
protection afforded by the statutory bond as far as reason and
logic will permit.
(See footnote 3)
***
A synthesis of the views expressed in the cases referred to
above would seem to be that . . . the statutory bond is to be
liberally construed to provide protection[.]
In the Syllabus of
Marsh v. Rothey, 117 W.Va. 94, 183 S.E. 914 (1936), this
Court discussed who could make a claim against the bond required by
W.Va. Code, 38-2-39
[2004], stating:
Necessary material furnished for, or necessary labor performed
on, a public structure under a contract with the general
contractor or subcontractor, is protected by the bond required by
Code, 38-2-39. Material supplied to, or labor performed for, a
furnisher of material on a public structure is not so protected.
(See footnote 4)
A subcontractor, ordinarily, is one to whom the principal
contractor sublets a portion or even all of the contract itself.
A
materialman, ordinarily, is one from whom the principal
contractor or a subcontractor secures material of a general type
for use on the structure.
(Emphasis added.)
(See footnote 5)
Nationally, a number of reported decisions have addressed the issue of whether
a party who provides labor or materials to a public construction project should be classified
as a materialman or as a subcontractor _ for purposes of determining the availability of
a construction bond to guarantee the payment of the party's supplier. Some cases involve
federal courts applying the Miller Act, 49 Stat. 793, 794, as amended, 40 U.S.C. secs. 270a
and 270b, which provides for similar bonds on certain federally-funded construction projects.
Other cases involve state statutes similar to
W.Va. Code, 38-2-39 [2004], sometimes referred
to as Little Miller Acts.
A recent and well-researched opinion discussing the subcontractor/materialman
distinction, and particularly the issue of whether a subcontractor must have necessarily
performed work at the construction site, is Vulcraft v. Midtown Business Park, Ltd., 110
N.M. 761, 800 P.2d 195, 197 (1990). In Vulcraft, the court stated:
Two divergent lines of authority are urged upon us to define
subcontractor. One line requires that work must be done at
the construction site for a party to qualify as a subcontractor. As
a Louisiana court articulated its view:
[A] subcontractor is a worker who actually
participates in the building or erection of the
edifice. A materialman is one who supplies
material either manufactured or fabricated for use
in that building. If the fabricator of material does
not engage in any process that incorporates the
item furnished into the immovable under
construction, he is a materialman. It matters not
whether his product is procured from another
manufacturer and delivered unchanged to the
building site or if it is shaped by him from other
materials before it is delivered to the job site.
Leonard B. Hebert, Jr. & Co. v. Kinler, 336 So.2d 922, 924
(La.App.1976) [footnote and additional citations omitted].
The alternative view is articulated in Theisen v. County of Los
Angeles, 54 Cal.2d 170, 183, 352 P.2d 529, 537-38, 5 Cal.Rptr.
161, 169-70 (1960) (in bank):
[T]he essential feature which constitutes one a
subcontractor rather than a materialman is that in
the course of performance of the prime contract
he constructs a definite, substantial part of the
work of improvement in accord with the plans and
specifications of such contract, not that he enters
upon the job site and does the construction there.
We are not here concerned with the mere
furnishing of materials from which doors were to
be constructed by the general contractor nor are
we interested in the sale of standard stock-in-trade
doors. Specifically we are dealing with a contract
whereby the doors were to be fabricated
according to the specifications of the prime
contract and as a constituent part of the
construction of the public improvement which
was the subject of the contract. We do not accept
the view of some other jurisdictions that to be a
subcontractor one must install work at the site of
the improvement. Rather, we conclude that one
who agrees with the prime contractor to perform
a substantial specified portion of the work of
construction which is the subject of the general
contract in accord with the plans and
specifications by which the prime contractor is
bound has charge of the construction of that
part of the work of improvement and is a
subcontractor although he does not undertake to
himself incorporate such portion of the projected
structure into the building.
(Citations omitted); see Piping Specialties Co. v. Kentile, Inc.,
229 Cal.App.2d 586, 589, 40 Cal.Rptr. 537, 539 (1964)
(emphasizing the meaning of a stock-in-trade item as being
whether or not the item is one which manufacturers stand ready
to produce and deliver, on order, according to designs already in
existence and emphasizing meaning of substantial as
important or material).[footnote and additional citations
omitted].
After a review of case law from across the nation, the Vulcraft court concluded:
We adopt, generally, the latter rule as enunciated in Theisen that does not require a subcontractor to have done work at the
construction site, as being in accord with our statutory structure
and precedent.
***
To qualify as a subcontractor, the party must perform some
portion of the work for which the owner originally contracted.
It is not necessary that the work be done at the construction site,
but work must be performed to the contract's plans and
specifications. The work can be performed on material supplied
to another subcontractor of the contractor, but the material
cannot be generic, stock, off-the-shelf items or items generally
available without modification-it must be fabricated uniquely or
specially by the contractor for the requirements of the particular
project. [citations omitted]
The work performed must also be substantial. We are not
concerned with a relatively small expenditure of labor in relation
to a contract mainly for material. We note that the substantiality
requirement accords with the statute's effect of creating privity
with the owner. It gives notice that the supplier/subcontractor
will be acting as an agent, allowing the owner to take protective
steps to insure the party is responsible, and the requirement
limits the scope of those able to file a lien.
Vulcraft,
supra, 110 N.M. at ___, 800 P.2d at 197-201.
Minnesota addressed the subcontractor/materialman distinction in connection
with a public construction bond in
Weyerhaeuser Co. v. Twin City Millwork Co., 291 Minn.
293, 191 N.W.2d 401 (1971). The
Weyerhauser court stated:
As we have suggested, a basic question is whether the prime
contractor can be expected to have notice of plaintiff's
participation in the project. There is always a question of
whether one who furnishes labor or material is so remote the
prime contractor cannot reasonably protect his interest. It is for
this reason that some courts have insisted on labor and material
being furnished at the job site where the contractor can observe
what is being done. The point at which the cutoff is appropriate
must necessarily be somewhat arbitrary. Suffice it to say that the
almost universal rule permits protection to materialmen who sell
to subcontractors but does not allow recovery by those who sell
standard products to materialmen.
In Clifford F. MacEvoy Co. v. United States, 322 U.S. 102,
108, 64 S.Ct. 890, 894, 88 L.Ed. 1163, 1168 (1944), a leading
case which deals with the payment bond required from
contractors by [Secs.] 1 and 2 of the Miller Act, 49 Stat. 793,
794, as amended, 40 U.S.C.A., secs. 270a and 270b, the United
States Supreme Court summarized the problem thus:
***
'The Miller Act itself makes no attempt to define
the word 'subcontractor.' We are thus forced to
utilize ordinary judicial tools of definition.
Whether the word includes laborers and
materialmen is not subject to easy solution, for the
word has no single, exact meaning. In a broad,
generic sense a subcontractor includes anyone
who has a contract to furnish labor or material to
the prime contractor. In that sense Miller was a
subcontractor. But under the more technical
meaning, as established by usage in the building
trades, a subcontractor is one who performs for
and takes from the prime contractor a specific part
of the labor or material requirements of the
original contract, thus excluding ordinary laborers
and materialmen.
'Practical considerations underlying the Act
likewise support this conclusion. Congress cannot
be presumed, in the absence of express statutory
language, to have intended to impose liability on
the payment bond in situations where it is difficult
or impossible for the prime contractor to protect
himself. The relatively few subcontractors who
perform part of the original contract represent in
a sense the prime contractor and are well known
to him. It is easy for the prime contractor to
secure himself against loss by requiring the
subcontractors to give security by bond, or
otherwise, for the payment of those who contract
directly with the subcontractors. [citations
omitted]. But this method of protection is
generally inadequate to cope with remote and
undeterminable liabilities incurred by an ordinary
materialman, who may be a manufacturer, a
wholesaler or a retailer. Many such materialmen
are usually involved in large projects; they deal in
turn with innumerable sub-materialmen and
laborers. To impose unlimited liability under the
payment bond to those sub-materialmen and
laborers is to create a precarious and perilous risk
on the prime contractor and his surety. To
sanction such a risk requires clear language in the
statute and in the bond so as to leave no
alternative. Here the proviso of Section 2(a) of the
Act forbids the imposition of such a risk, thereby
foreclosing Tomkins' right to sue on the payment
bond.'
***
Two other Federal cases deserve comment: United States for
Use of Wellman Engineering Co. v. MSI Corp. (2 Cir.) 350 F.2d
285 (1965); J. W. Cooper Const. Co. v. Public Housing
Administration (10 Cir.) 390 F.2d 175 (1968). In allowing
recovery under the Miller Act to a remote supplier, the court in
Wellman held the purchaser to be a subcontractor although the
company did not perform any work on the job site. There, as in
the instant case, the material furnished was built to
specifications and was not generally available on the open
market. A similar result was reached in the Cooper case where
the items ordered were kitchen cabinets furnished according to
plans and specifications.
Massachusetts and California have also passed on the question.
Holt & Bugbee Co. v. City of Melrose, 311 Mass. 424, 41
N.E.2d 562, 141 A.L.R. 319, involved millwork. Recovery was
allowed the remote supplier of lumber notwithstanding the fact
the purchaser took no part in the installation of the paneling,
rails, newel posts, trim, and stair stock which it built pursuant to
contract with the prime contractor.[
(See footnote 6) ] Theisen v. County of Los
Angeles, 54 Cal.2d 170, 5 Cal.Rptr. 161, 352 P.2d 529 (1960),
as in the instant case, involved the manufacture of doors. The
California court, relying on two Minnesota cases, Illinois Steel
Warehouse Co. v. Hennepin Lbr. Co., 149 Minn. 157, 182 N.W.
994; and Pittsburg Plate Glass Co. v. Sisters of the Sorrowful
Mother, 83 Minn. 29, 85 N.W. 829, expressed a view with
which we are in accord (54 Cal.2d 183, 5 Cal.Rptr. at 169, 352
P.2d 537[.]
(See footnote 7)
291 Minn. at ____, 191 N.W.2d at 403-405 (footnotes omitted).
(See footnote 8)
In U. S. for Use and Benefit of Parker, 477 F.Supp. 400, 411 (M.D.Pa. 1979),
the district court stated:
One of the most important factors to consider is the nature of
the material or service supplied by the alleged subcontractor to
the prime contractor. For example, a party who supplies fungible
goods which are a part of his general inventory, such as sand
and gravel, and the production of which does not require a
specialized or customized manufacturing process in order to
meet specifications of the prime contract is generally held to be
a material supplier rather than a subcontractor regardless of the
relationship of the cost of the materials which he supplies to the
cost of the entire project. See, e.g. Brown & Root, Inc. v.
Gifford-Hill & Co., 319 F.2d 65 (5th Cir. 1963); United States
ex rel. Pioneer Steel Co. v. Ellis Construction Co., 398 F.Supp.
719 (E.D.Tenn.1975). On the other hand, if an item is to be
custom manufactured by the purported subcontractor according
to the specifications found in the prime contract and the
purported subcontractor bears a portion of the responsibility for
the design and fabrication of the goods including the
responsibility to prepare shop drawings in accordance with
prime contract specifications, then it is likely that the
relationship between the prime contractor and the purported
subcontractor is sufficient to justify recovery by the latter's
material suppliers under the Miller Act. See, e.g., United States
ex rel. Gulfport Piping Co. v. Monaco & Son, Inc., 222 F.Supp.
175 (D.Md.1963), Rev'd on other grounds, 336 F.2d 636 (4th
Cir. 1964). Of course, custom manufacturing by itself is not
sufficient. To a certain extent, every material supplier is required
to provide to the prime contractor materials in accordance with
contract specifications. Thus, in Aetna Casualty & Surety Co. v.
United States ex rel. Gibson Steel Co., 382 F.2d 615 (5th Cir.
1967), the Court found a contractor-subcontractor relationship
lacking between the prime contractor and the purported
subcontractor because although the latter performed custom
manufacturing, none of the items which it made were complex
but rather consisted of simple components such as stairs and
ladders. The Court did indicate, however, that the fact that the
purported subcontractor was required to prepare the shop
drawings and that it had no inventory of the items to be
produced weighed on the side of a finding that a
contractor-subcontractor relationship existed. See also Miller
Equipment Co. v. Colonial Steel & Iron Co., 383 F.2d 669 (4th
Cir. 1967), Cert. denied, 390 U.S. 955, 88 S.Ct. 1049, 19
L.Ed.2d 1148 (1968).
In Sparks Const., Inc. v. Newman Bros., Inc., 51 Ala.App. 690, ___, 288 So.2d
749, 752-753 (Ala.Civ.App. 1974), the court found that a structural steel provider was a
subcontractor for purposes of a public construction bond:
Applying the above stated reasoning to the instant case, it is
clear that B & H was to furnish all structural steel, ornamental
iron, and miscellaneous work for Sparks. All of the above was
to be in strict accord with plans and specifications. The total
order from B & H called for some $57,598.
***
This court is of the opinion that the agreement between Sparks
and B & H was a substantial part of the overall contract between
Sparks and the board of education, and that B & H was a
subcontractor within the purview of Ala.Code, Tit. 50, [sec.] 16
(1940). Much of the work had to be custom fabricated to meet
the specifications of the elementary school building under
construction. We feel the purchase order agreement between
Sparks and B & H adequately reflects a substantive portion of
the overall contract, and further, served notice on Sparks that the
material must be custom fabricated.
Since B & H is a subcontractor, Newman, being at least a
materialman to the subcontractor, is entitled to the protection
afforded by the bond . . ..
In another case involving the furnishing of structural steel for a public
construction project, LaGrand Steel Products Co. v. A.S.C, 108 Idaho 817, ___, 702 P.2d
855, 857 (1985), the court stated:
In this case the central facts-undisputed or found by the trial
court upon substantial evidence-are as follows. The prime
contract between the State of Idaho and A.S.C. was
approximately $14,600,000. The contract between A.S.C. and
Steel Management totaled approximately $1,376,548. The
purchase order between A.S.C. and Steel Management was a
relatively complex document, making reference to provisions in
the prime contract. Steel Management was to provide custom
fabrication of the steel provided by LaGrand. This fabrication
involved cutting beams to required length, drilling holes,
welding plates, and prime painting. The work was not unduly
complicated. It was performed exclusively at Steel
Management's facility. Steel Management did not erect or
supervise the erection of the fabricated steel on the job site.
Labor involved in the fabrication totalled approximately
10,000 man hours billed at a cost of $100,000. A.S.C. required
Steel Management to submit shop drawings outlining the
fabrication of the steel. Steel Management subcontracted this
work to an engineering firm. Steel Management received
progress payments as the fabrication work progressed, less five
percent retainage held until all materials were incorporated into
the work and accepted by the State. A.S.C. required and
obtained personal guarantees of contract performance from the
principals and owners of Steel Management.
These factors present a mixed picture-some auguring in
support of subcontractor status and some against it. But in light
of the subcontractor definition and its underlying purpose, we
deem it particularly significant that the contract between A.S.C.
and Steel Management embraced more than one million dollars
and constituted approximately ten percent of the total prime
contract in a major public works project. A contract of such
economic dimension connotes a substantial, important
relationship with the prime contractor. It is also noteworthy that
the prime contractor deemed Steel Management's role in the
project sufficiently important to secure personal performance
guarantees. Considering these factors in conjunction with the
others, we conclude Steel Management had a substantial and
important relationship with the prime contractor. Accordingly,
we hold that Steel Management was a subcontractor within the
meaning of I.C. § 54-1927 et seq. LaGrand is entitled to recover
on the bond.
In another structural steel case, Illinois Steel Warehouse Co. v. Hennepin, 149
Minn. 157, ___, 182 N.W. 994, 995 [1921], the court stated:
Whether the Avery Company was a contractor or a
materialman within the meaning of the lien law depends on the
nature of the contract which it undertook to perform. It
contracted to furnish a substantial part of the steel 'fabricated'
as required by the plans and specifications. This necessarily
required the company to do the work of 'fabrication,' or cause
it to be done, and placed the company in the class of contractors
as distinguished from the class of materialmen under the lien
law. That the company, instead of performing the contract itself,
performed it through a subcontractor did not relieve the
company from its obligation to do the 'fabricating,' nor change
its relation to the building from that of a contractor to that of a
materialman. It follows that Boorman, to whom the contract was
sublet by the Avery Company, and who actually performed it,
was a subcontractor within the lien law.
And in yet another structural steel case, Blue Tee Corp. v. CDI Contractors,
Inc., 247 Neb. 397, 529 N.W.2d 16 (1995), the court stated:
The issue in this case is whether Northwestern was a
subcontractor or a materialman for the purposes of the Nebraska
Construction Lien Act. If Northwestern was a subcontractor for
CDI, Blue Tee is entitled to protection under the Nebraska
Construction Lien Act as a supplier to a subcontractor; if
Northwestern was a materialman to CDI, Blue Tee is not
entitled to a lien.
CDI was the general contractor for the construction of a
department store-Dillard's at Oakview Mall in Omaha. CDI
accepted Northwestern's bid to provide structural steel for the
project. Northwestern ordered raw steel from Blue Tee. Blue
Tee delivered the steel and billed Northwestern $108,070.09 for
the material. The date of the last delivery was on or about
November 1, 1990. The steel was fabricated by Northwestern
off the construction site and was installed by Davis Erection
Company.
According to Blue Tee's expert witness, John Rupprecht, steel
fabrication is the process of cutting, drilling, plating, and
otherwise altering raw steel sections to exact specifications such
that the sections may be assembled into the framework of a
building. Rupprecht also stated that, as in this case, fabrication
must be done in a steel fabrication facility and cannot be done
at a jobsite. He testified that, after steel has been fabricated for
a particular project, it has only scrap value if it is not
incorporated into that project or an identical project. Rupprecht
also stated that the work completed by Northwestern constituted
a definite and substantial portion of the project. Upon
cross-examination, Rupprecht admitted that fabrication of steel
could be as simple as cutting a piece of steel to a certain length.
***
This court has previously attempted to define the differences
between a subcontractor and a materialman. We have stated:
[T]he essential feature which constitutes one a
subcontractor rather than a materialman is that in
the course of performance of the prime contract
he constructs a definite, substantial part of the
work of improvement in accord with the plans and
specifications of such contract, not that he enters
upon the jobsite and does the construction there.
(Emphasis omitted.)
Ideal Basic Industries v. Juniata Farmers, 205 Neb. 611, 615,
289 N.W.2d 192, 195 (1980) (quoting 53 Am.Jur.2d Mechanics'
Liens § 72 (1970)).
***
The object of the mechanic's lien being to secure the claims of
those who have contributed to the erection of a building, it
should receive the most liberal construction to give full effect to
its provisions.
***
In the instant case, Northwestern cut, drilled, welded, and
otherwise fabricated raw steel to the exact specifications
required by CDI. Expert testimony established that
Northwestern's work on the project constituted a substantial
share of the construction of the department store. Despite the
evidence that Northwestern was a materialman, we recognize
the contribution of labor as the foremost indicium of
subcontractor status.
247 Neb. at ___, 529 N.W.2d at 18-21.
In
U.S. for Use and Ben. of Conveyor Rental v. Aetna, 981 F.2d 448, 451-452
(9
th Cir. 1992), the court stated:
Generally, courts have found the following factors weigh in
favor of a subcontractor relationship: (1) the product supplied is
custom fabricated ; (2) the product supplied is a complex
integrated system; (3) a close financial interrelationship exists
between the companies; (4) a continuing relationship exists with
the prime contractor as evidenced by the requirement of shop
drawing approval by prime contractor or the requirement that
the supplier's representative be on the job site; (5) the supplier
is required to perform on site; (6) there is a contract for labor in
addition to materials; (7) the term subcontractor is used in the
agreement; (8) the materials supplied do not come from existing
inventory; (9) the supplier's contract constitutes a substantial
portion of the prime contract; (10) the supplier is required to
furnish all the material of a particular type; (11) the supplier is
required to post performance bond; (12) there is a backcharge
for cost of correcting supplier's mistakes; and (13) there is
system of progressive or proportionate fee payment.
Generally, cases have found the following factors tend to
weigh in favor of a materialman relationship: (1) a purchase
order form is used by the parties; (2) the materials come from
preexisting inventory; (3) the item supplied is relatively simple
in nature; (4) the contract is a small percentage of the total
construction cost; and (5) sales tax is included in the contract
price. [multiple footnotes citing cases omitted.]
In a structural steel case where the court found the company that provided the
structural steel for the project was a materialman and not a subcontractor, U.S. for Use and
Ben. of Clark v. Lloyd T., 698 F.Supp. 665, 668 (S.D.Miss.1988), the court noted that the
. . . fabricated steel provided by Phoenix was considered in the
industry to be standard, not complex, fabrication and in fact,
the structural requirements [. . .] were so simple that the project
did not require the designs to be approved or prepared by a
structural engineer [and the] structural steel provided by
Phoenix was utilized only in the mezzanine area of the Project,
an area accounting for only fifteen percent of the total Project
size.
In Miller Equipment Co. v. Colonial Steel & Iron Co., 383 F.2d 669 (4th Cir.
1967), cert. den. 390 U.S. 955, 88 S.Ct. 1049, 19 L.Ed.2d 1148 (1968), another structural
steel case, the court stated:
The District Court concluded that Colonial was not a
subcontractor of Troitino, but simply a supplier of materials,
thus excluding Miller from the coverage of the bond. The
following subordinate findings account for the opinion of the
District Court that Colonial was no more than a materialman:
***
7. * * * Little, if any, discretion was vested in
Colonial as to the fabrication of the structural
steel as the design and computations required
were derived from the drawings of the Engineers
and the ASC Manual. Thus, the Court concludes
that Colonial was merely a materialman in
connection with the work on project 614.
Our opinion, however, is that despite the form of the written
contract between Troitino and Colonial, Colonial in actuality
was a subcontractor as envisaged by the Act and MacEvoy.
Certainly Colonial was no ordinary materialman. The amount
due it for successful performance of its contract with Troitino
was $115,000.00, more than 15% Of the sum due Troitino under
the prime contract and 64% Of item 20, a fundamental provision
of that contract because it was the specification for structural
steel. The Troitino-Colonial agreement called not for the mere
supply of materials but for the custom fabrication of massive
girders and their accessories, key and integral components of the
bridge, designed and fabricated to mesh precisely in their final
assembly on the job-site. See Travelers Indem. Co. v. United
States, 362 F.2d 896 (9 Cir. 1966); United States v. MSI Corp.,
350 F.2d 285 (2 Cir. 1965); compare United States for Use of
Bryant v. Lembke Constr. Co., 370 F.2d 293 (10 Cir. 1966). It
is of little moment here that Troitino designated the Colonial
agreement as a 'purchase order' for the steel. Nor is it surprising
that Colonial neither contributed to the bond premium nor
subscribed to Clause 21 and Standard Form 19-A. Troitino
never asked it to do so. We cannot posit Colonial's status as
materialman or subcontractor merely upon Troitino's neglect to
enforce its contract with the government, or to require that all
subcontractors contribute to the premium.
383 F.2d at 674.
Having reviewed the foregoing case law, we turn to the issues in the instant
case. March and the Sureties made two principal arguments in the District Court as to why
_ under the undisputed facts recited in the District Court's order _ Titan should be regarded
as a materialman, and not a subcontractor:
. . . March and the Sureties assert that an entity's status as a
materialman or subcontractor is contractually defined, and that,
even if such status is not contractually defined, there is
nonetheless a requirement that one physically perform work at
the Project site to be deemed a subcontractor.
(District Court order certifying questions.)
Neither of these arguments is persuasive in the instant case.
March's and the Sureties' argument that in order to qualify as a subcontractor
a party must perform work on the job site has been rejected by a wide range of state and
federal jurisdictions, as demonstrated supra. These jurisdictions have concluded that a party
who performs a substantial part of the contract for the principal contractor may be a
subcontractor for purposes of a public construction bond, even if the contracted-for work is
not performed on the job site itself. See Vulcraft, supra.
The reasonableness of this conclusion may be shown by imagining an instance
where a public works contract calls for the construction and installation on a prepared site
of a specialized, custom-made prefabricated building _ and where the prime contractor for
the project contracts with another company to create the building according to unique
contract specifications, and to deliver the custom-built building to a terminal near the
prepared site. Even though the company that custom-builds the building never goes on the
site where the building will ultimately sit, it would be absurd to be required to treat that
company as a mere materialman, when that company in fact performed the majority of the
contract. The plethora of cases cited hereinabove demonstrate that courts have readily and
very reasonably rejected any such absurd construction of the legislative intent in enacting a
public construction bond requirement.
As to March and the Sureties' argument that the parties' contractual
definition of the terms subcontractor or materialman is binding _ the discussion at note
8, supra, illustrates the even more uniform conclusion in the case law that it is the scope and
nature of a party's contribution to a public construction project that is most important,
although how that contribution is labeled by the parties may be a factor to be considered in
a court's analysis. See note 8, supra; see also Miller Equipment, supra.
In accord with the foregoing reasoning and the foregoing-discussed case law, we conclude and hold that for purposes of the public construction bond statute, W.Va. Code, 38-2-39 [2004], a party need not necessarily perform work at the construction job site itself
in order to be considered a subcontractor. To make the determination in a public
construction bond case whether a party that furnishes labor or materials for the project should
be classified as a subcontractor or as a materialman, a multi-factorial analysis should be used,
with no single factor being determinative. The core inquiry is whether the party in question
takes from the prime contractor a specific and substantial part of the labor or material
requirements of the original contract, thus excluding ordinary laborers and materialmen. See
Clifford F. MacEvoy Co. v. United States, 322 U.S. 102, 108, 64 S.Ct. 890, 894, 88 L.Ed.
1163, 1168 (1944).
IV.
Conclusion
The District Court's question is:
Under W.Va. Code, 38-2-39 (2003), is a steel fabricator
deemed to be a subcontractor where:
A. The steel fabricator enters a fixed-price contract
with the general contractor of a public works construction
project, pursuant to which the fabricator
i. Agrees to fabricate and deliver structural steel
components conforming to the construction project's unique
design specifications;
ii. Produces shop drawings for the fabricated steel
components based on the project's engineering calculations and
design specifications
iii. Submits its shop drawings for approval by the
project's architect and general contractor before fabricating the
structural steel components; and
iv. Delivers the fabricated steel components on a
delivery schedule based on construction progress;
B. The steel fabricator performs all physical
fabrication processes at its own facility, away from the project
site; AND
C. The fabricated steel components are not fungible
and not readily marketable without further modification?
Applying a multi-factorial analysis, this Court finds to be notable among the
factual premises of the District Court's question the fact that Titan specially fabricated
structural steel components that were created to the contract's unique design specifications
and were central to the project's ongoing progress; that Titan also produced shop drawings
for the fabricated steel components that had to be approved by the architect for the general
contractor March; and that the project-specific structural steel components provided by Titan
were not fungible products susceptible to ready use in other projects. Also notable is the
substantial percentage of the contracted-for project (more than one million dollars on a
twenty-million-dollar project) that was undertaken by Titan.
As the discussion and holdings in the foregoing-quoted cases illustrate (see, e.g., Vulcraft, Sparks Const., LaGrand Steel, Illinois Steel, Blue Tee Corp., Miller
Equipment, supra) these factors combine to render inescapable the conclusion that Titan was
far more than a mere materialman supplying a fungible product to the project. Titan was
clearly a subcontractor for purposes of W.Va. Code, 38-2-39 [2004]. Therefore, this Court's
answer to the District Court's certified question is Yes.
Having answered the certified question, the instant case is dismissed from the
docket of this Court and this Opinion is certified to the United States District Court for the
Northern District of West Virginia.
(See footnote 9)
Certified Question Answered
and Opinion Certified to the
United States District Court for the
Northern District of West Virginia.
Footnote: 1
We adopt the terms used by the District Court to identify and refer to the parties in
the instant case.
Footnote: 2
Infra made a motion for summary judgment on the materialman/subcontractor issue
in the District Court. The parties filed briefs, affidavits, and exhibits in connection with the
summary judgment motion, followed by the District Court's decision to refer a question of
law to this Court. This Court has those briefs, affidavits, etc. The parties stipulated to the
facts that are recited in the District Court's certified question order, quoted
infra. After this
Court accepted the certified question for review, March created a new affidavit and submitted
that affidavit with March's brief to this Court. The new affidavit downplayed the complexity
of the structural steel fabrication work that Titan contracted to perform and sought to thereby
factually undermine the claim that Titan was a subcontractor whose suppliers could make a
claim against March's bond. Although this new affidavit bears the style of the federal court
case from which the instant certified question originates, the affidavit was not filed in that
court. At oral argument before this Court, counsel for March cited the
de novo nature of this
Court's standard of review in certified question cases as authority for submitting a new
affidavit. However, this Court reviews
issues of law de novo in certified question cases _ not
issues of fact. Therefore, the new affidavit, which asserts facts and characterizations that
were not presented to or ruled upon by the district court, can be given no consideration by
this Court. We proceed upon the stipulated facts in the District Court's order.
Footnote: 3
This language from
Walker Machinery is consistent with
Tug River Lumber Co. v.
Smithey, 107 W.Va. 482, 490, 148 S.E. 850, 853 (1929), where this Court stated:
Conceding that there is no right of lien against the school
building, this bond, if only for the protection of the board, and
not for the protection of laborers and materialmen, would be
meaningless. In the terse words of one of our jurists, Courts
struggle to make public bonds answer public justice.
Footnote: 4
The present statute, thus read, gives liens only to general contractors and
subcontractors and persons contracting with them. Beyond those three classes, the statute
affords no protection.
Rosenbaum v. Price Const. Co., 117 W.Va. 160, 164, 184 S.E. 261,
263 (1936).
Footnote: 5
In
Marsh v. Rothey,
supra, this Court found that a supplier of crushed stone was a
materialman and not a subcontractor, where there was no evidence that the stone had been
crushed to a size unique to the project.
Footnote: 6
A subcontractor is one who has entered into a contract express
or implied, for the performance of an act, with a person who has
already contracted for its performance. And one who contracts
to supply materials manufactured or processed especially for the
general contractor and in accordance with special reference to
his plans and specifications or those by which he is bound
comes within that definition. It was not necessary that MacPhee
should have undertaken to install the finished products in
question in the city hall. The labor performed by him in milling
the interior trim for the additions and alteration of the building
was to all intents and purposes work performed in its
construction.
Holt & Bugbee Co. v. City of Melrose, 311 Mass. 424, ___, 41 N.E.2d 562, 563 (1942).
(internal citations omitted).
Footnote: 7
See the extended quotation from
Theisen in
Vulcraft,
supra.
Footnote: 8
Both parties to the instant appeal argue that in the instant case, weight should be
given to the terms that the parties used (or did not use) in their contractual documents. Infra
points to the fact that the March purchase order _ that set out specifications for the work that
Infra was going to do _ used the term subcontract to describe the parties' relationship.
(March claims that its use of the term subcontract was an error.) March and the Sureties
counter with the claim that March only requires parties actually working on a job site to sign
a standardized subcontractor contract form _ and that this form was not used with Infra.
Our research indicates that the use of a particular term in connection with a business
relationship is not considered to be a dispositive factor when making the
subcontractor/materialman distinction in connection with a public construction bond _
although the use of a particular term may be entitled to some weight. This issue was
discussed in Unadilla Silo Co., Inc. v. Hess Bros., Inc., 123 N.J. 268, 586 A.2d 226 (1991): . . . Unadilla's president, in his deposition, described both
Unadilla and Eco as materialmen, contending that if Unadilla
does not consider Eco to be a subcontractor, neither should this
Court. In our view, Unadilla's self-classification is not
controlling, especially because the terms subcontractor and
materialman may be interpreted differently, depending on the
context in which they are used. See Lyle Signs v. Evroks Corp., supra, 132 N.H. at 158, 562 A.2d at 787 (middle party described
itself as a material supplier in correspondence to general
contractor); cf. United States ex rel. Consolidated Pipe and
Supply Co. v. Morrison-Knudsen Co., supra, 687 F.2d at 134
(fact that contractual instrument was styled purchase order not
controlling on question whether supplier was subcontractor or
materialman); United States ex rel. Gulfport Piping Co. v.
Monaco and Son, Inc., 222 F.Supp. 175, 180-81 (D.Md.1963)
(although government engineer's telegram referred to middle
party as material supplier, court disregarded statement and
looked to substance of contract), rev'd on other grounds, 336
F.2d 636 (4th Cir.1964).
***
In determining whether a supplier of materials is a
subcontractor within the meaning of the Bond Act, we apply a
functional standard considering, among others, the following
factors: (1) whether the material supplier agreed to perform a
definite and substantial part of the same work that the general
contractor was obligated to perform; (2) whether the work was
performed according to plans and specifications in the original
contract; and (3) whether the materials required off-site
fabrication prior to installation at the job site. Further, a
subcontractor protected by the Bond Act must have agreed to
provide labor or materials for either the general contractor or
one of its subcontractors. Although on-site work may be a
factor in determining whether the material supplier performed
a definite and substantial amount of the work called for in the
original contract, on-site work is not a prerequisite to
subcontractor status.
Unadilla,
supra,
123 N.J. at ___, 586 A.2d at 236-237 [internal citations omitted].
It should be noted that whether a party is classified as a subcontractor or a
materialman for purposes of a public construction bond has no significance for other legal
purposes _ such as the application of workplace safety laws _ and
vice versa.
Footnote: 9
We have the benefit of amicus curiae briefs from the West Virginia Contractors'
Association and the Surety and Fidelity Association of America. Both amici urge this Court
not to rule in the instant case in a fashion that would inadvertently or improperly alter long-
settled practices and understandings in the construction business. We adhere to this stricture.
Our holding is squarely in line with the holdings of many jurisdictions, including the United
State Supreme Court, and it recognizes no duty by a party to a construction or bond
agreement that is not clearly spelled out in statutes that were enacted many years ago and
recognized by courts across this nation.