CONTRACTOR ENTERPRISES, INC.,
Per Curiam:
Kyle D. Ramey and Trina Ramey (hereinafter jointly referred to as
Appellants) appeal the June 27, 2008, summary judgment order of the Circuit Court of
Logan County. As a result of this order, Appellants' deliberate intention action brought
pursuant to West Virginia Code § 23-4-2(d)(2)(ii) (See footnote 1) against Contractor Enterprise, Inc.
(hereinafter Contractor Enterprise or employer) was dismissed. Appellants claim that
the lower court erred in its grant of summary judgment by not viewing the evidence in the
light most favorable to them as the non-moving party, and concluding that no genuine issue
of material fact existed regarding two of the five required statutory elements (See footnote 2) relevant to this
deliberate intent action. Specifically, the lower court found there was insufficient evidence
presented to support the existence of the elements of the employer having actual knowledge
of the unsafe working condition and the employer's intentional exposure of Mr. Ramey to
the unsafe working condition. W.Va. Code § 23-4-2(d)(2)(ii)(B) and (D). After due
consideration of the arguments of the parties in light of the record before us and the relevant
law, we affirm the decision of the circuit court.
The operator's ground control plan in place at the time of the accident included a drill pattern to keep the drill operator and drill at least four feet from the highwall's edge. The drill operator did not follow normal operating procedures by positioning the drill parallel with the existing highwall. This action exposed the drill operator to a hazard of falling over the highwall. If the drill had been positioned as the ground control plan stated, the drill would have been at least six feet from the highwall.
The MSHA report also contained the following description of the accident:
On Wednesday, March 2, 2005, at approximately 6:00 a.m., the first shift crew arrived at the parking area and received instructions from Randy Maynard, pit foreman. Maynard gave the drill crew, composed of Ramey and John Chambers, instructions for drilling the Stockton Pit.
Ramey and Chambers traveled to the Stockton bench and began drilling. Ramey finished the row of drillholes and the drill was moved to the center of the next section to be drilled. Ramey exited the drill and marked the next row of holes to be drilled. Ramey then moved his drill towards the edge of the highwall, parallel with the existing highwall, in close proximity to the next hole to be drilled. Ramey got out of the driller's compartment and was last seen standing between the drill access ladder and the edge of the highwall. Ramey slipped[ (See footnote 6) ] and fell over the 80-foot tall highwall. The distance between the highwall drill and the edge of the highwall was measured and found to be 23 inches.
The overall conclusion MSHA reached regarding the accident was summarized in the report
as:
Ramey positioned himself between the highwall drill and the edge of the highwall when he slipped or fell over the 80-foot highwall. The fall, which resulted in serious injuries,[ (See footnote 7) ] occurred because the victim was positioned in a hazardous location without a safety belt or line, where there was a danger of falling.
In the Root Cause Analysis section of the MSHA report, the cause of the
accident was identified as Mr. Ramey positioning himself within twenty-three inches of the
edge of the highwall without being tied off or secured in a manner that would have
prevented falling over the embankment. As a result of this finding the employer was cited
for a violation of 30 C.F.R. 77.1710 (g), which requires mining employees to be equipped
with safety belts and lines where there is danger of falling. As further noted in the Root
Cause section of the MSHA report, the employer took corrective action after the accident
by making an addition to the ground control plan requiring persons working six feet or less
from the edge of the highwall be tied off. Under no circumstances will anyone be working
within four feet of the edge of the highwall.
On March 2, 2007, Appellants filed a deliberate intent action pursuant to West
Virginia Code § 23-4-2(d)(2)(ii) against Contractor Enterprise claiming that the employer
exposed Mr. Ramey to a specific unsafe working condition without the proper training or
safety equipment and with the knowledge that the unsafe condition presented a high degree
of risk and strong probability of serious injury or death. Following the time period initially
allocated for discovery by the trial court, Contractor Enterprise moved for summary
judgment. Contractor Enterprise submitted a memorandum in support of its motion, with
the following documents attached: the Rameys' complaint, MSHA Report of Investigation,
deposition of Mr. Ramey, and a variety of training documentation the employer maintained
on Mr. Ramey. Contractor Enterprise also submitted a Daily and Onshift Report and
Preshift-Mine Examiner's Reports for the day of the accident as attachments to the reply it
filed to Appellants' amended response (See footnote 8) to the summary judgment motion. The evidence
Appellants relied on and supplied as attachments to their amended response to the summary
judgment motion included: Mr. Ramey's deposition, a Rule 26 Expert Witness Disclosure
in which Appellants' attorney outlined what he believed the testimony of the named mine
safety expert, H.S. Grose, would entail, (See footnote 9) and the affidavit of Mark Kennedy, a former
employee of Contractor Enterprise who had left the company's employ as a bull dozer
operator six weeks before the accident. (See footnote 10)
A hearing was held on the summary judgment motion on May 14, 2008, and
the order granting summary judgment to Contractor Enterprise was filed on June 27, 2008.
The core ruling in the order was that even when viewed in the light most favorable to
Appellants as the non-moving party, the evidence failed to demonstrate that a genuine issue
of material fact existed with regard to the elements of a deliberate intent action as set forth
in (B) and (D) of West Virginia Code § 23-4-2(d)(2)(ii).
Appellants thereafter petitioned this Court for review of the summary
judgment decision, and the appeal was granted on April 8, 2009.
According to the express provisions of Rule 56 of the West Virginia Rules of
Civil Procedure, summary judgment shall be rendered forthwith if the pleadings,
depositions, answers to interrogatories, and admissions on file, together with the affidavits,
if any, show that there is no genuine issue as to any material fact and that the moving party
is entitled to a judgment as a matter of law. W.Va. R. Civ. P. 56(c). The concept of
material fact and genuine issue were succinctly explained by the U.S. Court of Appeals
in the Eleventh Circuit as follows:
[a]n issue of fact is material if it is a legal element of the claim under the applicable substantive law which might affect the outcome of the case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248[,] 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986); Tipton v. Bergrohr GMBH-Siegen, 965 F.2d 994, 998 (11th Cir. 1992). It is 'genuine' if the record taken as a whole could lead a rational trier of fact to find for the nonmoving party. Id.
Allen v. Tyson Foods, Inc., 121 F.3d 642, 646 (11th Cir. 1997). We have further explained
that [a] motion for summary judgment should be granted only when it is clear that there is
no genuine issue of [material] fact to be tried and inquiry concerning the facts is not
desirable to clarify the application of law. Syl. Pt. 3, Aetna Cas. & Sur. Co. v. Federal Ins.
Co. of New York, 148 W.Va. 160, 133 S.E.2d 770 (1963). Thus, [t]he question to be
decided on a motion for summary judgment is whether there is a genuine issue of [material]
fact and not how that issue should be determined. Id. at Syl. Pt. 5.
We proceed with our review guided by these principles.
Appellants first argue that the affidavit of Mark Kennedy showed that
Contractor Enterprise had actual knowledge because Mr. Kennedy's sworn statements
establish that he had advised a supervisor at Contract Enterprises several weeks before Mr.
Ramey's accident that equipment was being operated too close to the highwall edges. The
affidavit did not state that Mr. Kennedy told anyone that drills were being operated too close
to the highwall edges. Consequently, we do not find that the assertions in the Kennedy
affidavit demonstrate that Contractor Enterprise was aware of the specific unsafe working
condition of drill operators working dangerously close to the edge of the highwall, nor does
it show that the employer was informed that Mr. Ramey was operating his drill too close to
the edge of the highwall.
According to his affidavit, Mr. Kennedy had worked for Contractor Enterprise as a bull dozer operator and his last day of work for the company was six weeks before Mr. Ramey's accident. In the affidavit, Mr. Kennedy made general statements as to his belief that the company pushed production over safety and that safety meetings conducted by the company consisted of signed attendance sheets without any instruction or training. With particular regard to work being done overly close to the edge of the highwall, Mr. Kennedy stated that he observed safety violations of the drilling machines operated by Kyle Ramey and that he had seen these machines placed so close to the highwall that the curtains on the machine could be seen from below. However, it is clear from the affidavit that Mr. Kennedy did not tell anyone about drilling machines being operated too close to the highwall edges. The following is the only statement in the affidavit indicating what Mr. Kennedy told the unnamed supervisor which is relevant to the statutory element of actual knowledge. As stated under oath by Mr. Kennedy,
the last day he worked at Snap Creek No. 1 Mine he was operating a bull dozer on the edge of a highwall. He advised the supervisor that this was too dangerous and refused to work the remainder of his shift. He further told the supervisor that the company was working people too close to the highwall edges without any regard to safety. He also told the supervisor someone was going to get hurt or killed.
As stated, even if an unnamed supervisor of Contractor Enterprise became aware of work
being done dangerously close to the edge of the highwall, Mr. Kennedy's statement would
only establish that some unidentified person was informed that Mr. Kennedy as a bull dozer
operator was exposed to the specific unsafe working condition of operating his bull dozer
too close to the edge of the highwall.
In addition to being unclear as to the name of the particular supervisor to
whom Mr. Kennedy made his statement, the affidavit does not reveal if the unnamed
supervisor had any role in supervising the drilling operations at the mine site or the extent
of the supervisor's authority or area of responsibility. The statement could have been made
to a supervisor having no real knowledge or responsibility regarding mining operations.
Furthermore, the statements in the affidavit regarding observing drilling machines being
operated so close to the edge of that highwall that the curtains of the machines were visible
from below apparently were not made to anyone. Thus Mr. Kennedy's statements fall short
of shedding any light on whether Contractor Enterprise had actual knowledge of drilling
equipment being operated closer to the edge of the highwall than the ground control plan
specified.
Appellants maintain that the proffered opinions of their safety expert also serve
to establish the element of actual knowledge. The record before us contains no submissions
as to the actual opinions held or sworn statements made by Appellants' expert. The only
item in the record regarding the expert's opinions is a document submitted with Appellants'
amended response to the motion for summary judgment styled Rule 26 Expert Witness
Disclosure. This document contains the representations of Appellants' attorney as to what
he opined would be the expert's position. Specific to the element of actual knowledge,
Appellants claim that the expert had the opinion that Contractor Enterprise did not perform
mandatory workplace inspections required by federal regulations to identify unsafe working
conditions. According to Appellants, in compliance with the reasoning of this Court's
decision in Ryan v. Clonch, 219 W.Va. 664, 639 S.E.2d 756 (2006), such failure to conduct
mandatory inspections bars Contractor Enterprise from denying that it possessed actual
knowledge of the hazard. Appellants reliance on Ryan is misplaced given the significantly
different facts in the case now pending.
The Ryan case involved an employer who admitted that it had failed to
perform a mandatory hazard inspection which would have revealed the unsafe working
condition that resulted in the injury on which the deliberate intent action was based. The
employer in Ryan then attempted to claim that it had no actual knowledge of the unsafe
working condition. We concluded in syllabus point six of Ryan that where . . . [an]
employer fail[s] to perform a reasonable evaluation to identify hazards in the workplace in
violation of a statute, rule or regulation imposing a mandatory duty to perform the same, the
performance of which may have readily identified certain workplace hazards, the . . .
employer is prohibited from denying that it possessed . . . [actual knowledge] of the hazard
asserted in the deliberate intent action. Id. at 667, 639 S.E.2d at 759.
The facts in the pending case are clearly distinguishable from those considered
in Ryan as the employer here did not fail to carry out its inspection duties. Contractor
Enterprise supplied the lower court with inspection documents - without apparent objection
to their submission - representing that pre-shift and on-shift worksite inspections had been
conducted the day of and prior to the accident involving Mr. Ramey. The employer thus
demonstrated it had complied with the federally required inspection schedule as MSHA
regulations mandate a minimum of daily inspection of mine sites for hazardous conditions. (See footnote 14) Hence we concur with the trial court's conclusion that actual knowledge could not be
imputed to the employer pursuant to our holding in Ryan because there was no failure on the
part of the employer to conduct mandatory inspections.
B. Intentional exposure
As we summarized in Tolley v. ACF Industries, Inc., 212 W.Va. 548, 558, 575
S.E.2d 158, 168 (2002), in order to establish the existence of intentional exposure in a
deliberate intent action there must be some evidence[] that with conscious awareness of the
unsafe working condition . . . an employee was directed to continue working in that same
harmful environment. Even if there was sufficient evidence of actual knowledge in this
case, we find no evidence that Contractor Enterprise instructed, ordered or directed Mr.
Ramey to operate his drill any closer to the edge of the highwall than the acceptable four
foot distance specified in the operational ground control plan that had been approved by
MSHA.
Appellants argument regarding proof of intentional exposure is not clearly
articulated. It appears Appellants are asserting that the element of intentional exposure
exists based upon the showing that Contractor Enterprise sent Mr. Ramey to a drill
site knowing that Mr. Ramey did not have adequate training, including instruction on following
the ground control plan. In other words, it is alleged that the employer knew Mr. Ramey
was completely unaware of the hazards of working too close to the edge of a highwall but
sent him to the highwall job site armed without knowledge of the dangerous condition or
without protection from the hazard in the form of equipment such as a safety harness.
Our examination of the record, specifically the MSHA accident investigation
report, Mr. Ramey's deposition and the training documentation Contractor Enterprise
supplied to the lower court, discounts the proposition that Mr. Ramey was untrained and
unaware of the dangers posed by working too close to the edge of a highwall. The MSHA
report revealed that Mr. Ramey had nearly two years mining experience, and a total of four
years experience as a drill operator at mines and construction sites. During his deposition,
Mr. Ramey said that he had been trained by Contractor Enterprise for at least three hours on
the actual operation of the drill. While he also said in response to questioning that he could
not remember what a ground control plan is, not knowing and not remembering are two very
different things _ especially considering the extensive memory loss Mr. Ramey admittedly
sustained as a result of the fall from the highwall edge. Training was also addressed in the
MSHA report. The report said that training had been conducted by Contractor Enterprise
as mandated by federal regulation. Hazard training is expressly required under MSHA
regulations. 30 C.F.R. § 48.11 (before miners can commence their duties, a company is
required to provide the workers with hazard training which must include [h]azard
recognition and avoidance). Mr. Ramey's attendance at the requisite training sessions was
shown through Contractor Enterprise's submission of training attendance records.
In sum, our review of the meager record (See footnote 15) in this case supports the lower
court's conclusion that there is no genuine issue as to material facts regarding the deliberate
intent statutory elements of actual knowledge and intentional exposure. W.Va. Code § 23-4-
2(d)(2)(ii) (B) and (D). Mr. Ramey alleged in his complaint that he was ordered by Contract
Enterprise to work in the hazardous working condition of operating a drill less than four feet
from the edge of a highwall without being properly trained or equipped. There is no
suggestion in the record that Mr. Ramey was required by the employer to operate his drilling
equipment less than four feet from the highwall edge. The record before us reveals that the
hazardous condition in this case did not occur until Mr. Ramey deviated from the ground
control plan and moved his drilling equipment to within twenty-three inches of the highwall.
As to training, the record before us shows that the employer provided Mr. Ramey with all
MSHA required training, and there is no indication that Mr. Ramey requested additional
instruction regarding the operation of the drilling equipment or relevant safety issues. It is
also evident from our review of the record we have that on the date of the incident the
employer was not required to provide safety equipment such as a harness or lanyard unless there was a danger of falling. The safe distance prescribed in the MSHA approved ground
control plan in effect at the time of the accident was four foot from the edge of the
highwall. (See footnote 16) Accordingly, we affirm the lower court's grant of summary judgment in this
case.