Link to PDF file
664 S.E.2d 724
IN THE SUPREME COURT OF APPEALS OF WEST VIRGINIA
January 2008 Term
________________
No. 33520
________________
JERRY NEAL AND KAREN NEAL,
Plaintiffs Below, Appellants,
V.
J.D. MARION, DAVID JORDAN, BEVERLY JORDAN,
SANDY KESSELL, LOMBARDO REALTY COMPANY
N/K/A NEW MILLENNIUM CORPORATION, and
THE CITY OF CHARLESTON,
Defendants Below, Appellees,
______________________________________________________
Appeal from the Circuit Court of Kanawha County
The Honorable Irene C. Berger, Judge
Civil Action No. 04-C-2670
REVERSED AND REMANDED
_____________________________________________________
Submitted: February 26, 2008
Filed: June 18, 2008
David L. Grubb
Cameron S. McKinney
The Grubb Law Group
Charleston, West Virginia
Attorney for Appellants
|
Josef A. Horter
H. Jerome Sparks
Hendrickson & Long, PLLC
Attorneys for Appellee J.D. Marion |
JUSTICE BENJAMIN delivered the opinion of the Court.
SYLLABUS BY THE COURT
1. The standard of review applicable to an appeal from a motion to alter
or amend a judgment, made pursuant to W. Va. R. Civ. P. 59(e), is the same standard that
would apply to the underlying judgment upon which the motion is based and from which the
appeal to this Court is filed. Syllabus point 1, Wickland v. American Travelers Life
Insurance Company, 204 W. Va. 430, 513 S.E.2d 657 (1998).
2. A circuit court's entry of summary judgment is reviewed de novo.
Syllabus point 1, Painter v. Peavy, 192 W. Va. 189, 451 S.E.2d 755 (1994).
3. Where the issue on appeal from the circuit court is clearly a question
of law or involving an interpretation of a statute, we apply a de novo standard of review.
Syllabus point 1, Crystal R.M. v. Charlie A.L., 194 W. Va. 138, 459 S.E.2d 415 (1995).
4. W. Va. Code, 55-2-6a, limits the time period in which a suit may be
filed for deficiencies in the planning, design, or supervision of construction of an
improvement to real property to ten years. Syllabus point 1, in part, Gibson v. West
Virginia Department of Highways, 185 W. Va. 214, 406 S.E.2d 440 (1991).
5. A cardinal rule of statutory construction is that significance and effect
must, if possible, be given to every section, clause, word or part of the statute. Syllabus
Point 3, Meadows v. Wal-Mart Stores, Inc., 207 W. Va. 203, 530 S.E.2d 676 (1999).
6. West Virginia Code § 55-2-6a (1983) sets an arbitrary time period after
which no actions, whether contract or tort, seeking damages for any deficiency in the
planning, design, surveying, observation or supervision of any construction or the actual
construction of any improvement to real property may be initiated against architects and
builders. This arbitrary time limit begins to run when the builder or architect relinquishes
access and control over the construction or improvement and the construction or
improvement is (1) occupied or (2) accepted by the owner of the real property, whichever
occurs first. Pre-existing statutes of limitation for both contract and tort actions continue to
operate within this outside limit. To the extent this Court's decisions in Shirkey v. Mackey,
184 W. Va. 187, 399 S.E.2d 868 (1990), and Gibson v. West Virginia Department of
Highways, 185 W. Va. 214, 406 S.E.2d 440 (1991), indicate otherwise, they are hereby
modified.
Benjamin, Justice:
The instant appeal arises from the Circuit Court of Kanawha County's
application of the West Virginia Architect and Builder's Statute of Repose, W. Va. Code
§55-2-6a (1983),
(See footnote 1) to dismiss, upon a motion for summary judgment, all claims asserted by
appellants Jerry Neal and Karen Neal (hereinafter collectively referred to as the Neals)
against appellee J.D. Marion (hereinafter Marion) in this civil lawsuit. In the underlying
action, the Neals, subsequent purchasers of a home constructed by Marion, asserted various
claims against Marion, including claims arising from the alleged concealment of construction
defects and fraudulent misrepresentations regarding the same.
(See footnote 2) The circuit court dismissed
all claims asserted against Marion upon finding that the action had been filed more than ten
years after construction was complete. Upon considered review of the record, argument of
the parties and applicable law, we reverse the circuit court's decision and remand this matter
for further proceedings.
I.
FACTUAL AND PROCEDURAL BACKGROUND
Appellee Marion constructed a home located at 522 Woodbridge Drive,
Charleston, West Virginia, which, upon completion of construction, was purchased by
appellees David and Beverly Jordan (hereinafter the Jordans) on February 23, 1994.
During the summer of 1996, the Neals entered into negotiations for the purchase of the
home. (See footnote 3) In their complaint, which was filed on October 1, 2004, the Neals allege that Marion
actively participated in the negotiations for this sale, including representing that there were
no problems with the foundation and that all prior repairs had been disclosed. Further,
Marion agreed to provide a warranty for future repairs which may become necessary should
the Neals purchase the home. (See footnote 4) On August 8, 1996, the Neals purchased the subject home.
Consistent with representations made during the negotiation process, Marion made several
undisclosed additional repairs subsequent to the Neals' purchase of the home.
Between October 2002 and May 2003, professional engineers inspected the
Woodbridge Road property on three occasions. (See footnote 5) As a result, a report was issued opining that
the foundation was severely flawed, unsafe and inadequate for the home's design and
location. Additionally, the report indicated that the foundation had undergone prior,
substandard repairs that had been actively concealed by walling in and covering up large
portions of the foundation such that a routine home inspection would not uncover the work.
On October 1, 2004, the Neals filed a six count complaint (See footnote 6) against the various
defendants. In the complaint, the Neals summarized their allegations stating:
Plaintiffs allege that the home constructed by Defendant Marion
was not constructed as expressly or impliedly warranted at the
time the home was sold. Plaintiffs further allege that
Defendants: (1) fraudulently and materially misrepresented the
condition and quality of the home and the nature and extent of
prior repairs to the home; (2) subsequently refused to remedy
the problems and/or cancel the contract when requested by
Plaintiffs; (3) took deliberate action to actively conceal the
defective construction so that it would not be discovered
through a reasonable inspection; (4) committed a series of unfair
or deceptive acts or practices; and (5) otherwise violated the
law[.]
With respect to Marion, the Neals' complaint specifically alleged that he: expressly and
impliedly warranted the quality, safety, and workmanship of the home's construction;
performed several repairs to the home after the sale to the Jordans pursuant to the warranties;
concealed or failed to disclose prior repairs to the Neals prior to the sale; expressly warranted
the quality, safety, and workmanship of the home's construction to the Neals at the time the
Neals were considering and negotiating the purchase of the home; and promised to make
repairs if the Neals purchased the home. (See footnote 7)
In January 2006, Marion filed a motion for summary judgment arguing that
W. Va. Code §55-2-6a barred the Neals' claims against him because the complaint was filed
more than ten (10) years after construction was complete and their complaint alleges that
the design and/or construction of the house's foundation was flawed. In response, the Neals
set forth their allegations regarding representations about prior repairs and the condition of
the foundation made by Marion on August 8, 1996, during the negotiations for their purchase
of the home. Additionally, the Neals provided the circuit court with their engineers' report
and Marion's discovery responses. The Neals argued that their allegations of fraudulent
concealment and misrepresentation and Marion's 1996 representations precluded summary
judgment.
The circuit court ruled on Marion's motion prior to the scheduled hearing on
the matter and dismissed the Neals' claims against Marion. The entirety of the circuit court's
order states:
FILED AND PENDING before this Court is J.D. Marion's
Motion for Summary Judgment. After having reviewed and
considered Defendant Marion's motion for summary judgment
and memorandum in support thereof, and Plaintiff's [sic]
Memorandum of Law in Opposition to Defendant J.D. Marion's
Motion for Summary Judgment, this Court makes the
following FINDINGS OF FACT and CONCLUSIONS OF
LAW:
1) There is no genuine issue of material fact
that the Defendant, J.D. Marion constructed the
house located at 522 Woodbridge Drive in
Charleston, West Virginia, prior to February 23rd,
1994.
2) The Complaint herein was filed on
October 1st, 2004.
3) The Plaintiffs' claims against Defendant
Marion are time barred pursuant to West Virginia
Code §55-2-6a.
WHEREFORE, for the foregoing reasons, it is ORDERED,
ADJUDGED and DECREED that Defendant Marion's motion
for summary judgment is granted and all of the Plaintiff's
claims against Defendant Marion are dismissed, with prejudice,
preserving the Plaintiffs' objections for the record.
The Neals timely filed a motion to alter or amend the summary judgment order, pursuant to
Rule 59(e) of the West Virginia Rules of Civil Procedure arguing that their claims based
upon fraud and misrepresentations during the negotiations for their purchase of the property
were not subject to the provisions of W. Va. Code §55-2-6a. The Neals' Rule 59 motion was
summarily denied and this appeal follows.
II.
STANDARD OF REVIEW
The instant appeal presents itself to this Court upon the circuit court's denial
of the Neals' Rule 59(e) motion to alter or amend the circuit court's summary judgment
order invoking W. Va. Code §55-2-6a to dismiss their claims asserted against Marion. We
have previously held that [t]he standard of review applicable to an appeal from a motion
to alter or amend a judgment, made pursuant to W. Va. R. Civ. P. 59(e), is the same standard
that would apply to the underlying judgment upon which the motion is based and from
which the appeal to this Court is filed. Syl. pt. 1, Wickland v. American Travelers Life
Insurance Company, 204 W. Va. 430, 513 S.E.2d 657 (1998). It is well settled in this
jurisdiction that [a] circuit court's entry of summary judgment is reviewed de novo. Syl.
pt. 1, Painter v. Peavy, 192 W. Va. 189, 451 S.E.2d 755 (1994). Our review of the circuit
court's application of W. Va. Code § 55-2-6a in this matter is likewise de novo. Syl. Pt. 1, Crystal R.M. v. Charlie A.L., 194 W. Va. 138, 459 S.E.2d 415 (1995) (Where the issue on
appeal from the circuit court is clearly a question of law or involving an interpretation of a
statute, we apply a de novo standard of review.). Thus, we are afforded plenary review of
matters raised in the instant appeal.
III.
DISCUSSION
Appellants' primary argument on appeal is that the circuit court erred by
finding that W. Va. Code §55-2-6a barred their claims asserted against Marion, but
particularly their fraud, material misrepresentation and conspiracy claims.
(See footnote 8) Marion responds
that the circuit court did not err in its application of W. Va. Code §55-2-6a to dismiss all
claims. According to Marion, only the date upon which the home's construction was
completed and the date upon which the complaint was filed are relevant because W. Va.
Code § 55-2-6a precludes any tort or contract claim not filed within 10 years of the
completion of construction according to this Court's decision in
Shirkey v. Mackey, 184
W. Va. 187, 399 S.E.2d 868 (1990). The Neals counter that their fraud and
misrepresentation claims arise from separate acts which are distinct from the original
construction. Fairly articulated, the Neals' argument is that the date on which construction
is complete is the relevant or dispositive factor for application of W. Va. Code §55-2-6a in
those instances where the condition of the original design or construction has not been
altered or fraudulently misrepresented subsequent to completion of construction. However,
they contend subsequent acts which alter, conceal or misrepresent the condition of the
original construction operate start the statute's time limits anew. We agree with this
argument.
West Virginia Code §55-2-6a provides:
No action, whether in contract or in tort, for indemnity or
otherwise, nor any action for contribution or indemnity to
recover damages for any deficiency in the planning, design,
surveying, observation or supervision of any construction or the
actual construction of any improvement to real property, or, to
recover damages for any injury to real or personal property, or,
for an injury to a person or for bodily injury or wrongful death
arising out of the defective or unsafe condition of any
improvement to real property, may be brought more than ten
years after the performance or furnishing of such services or
construction: Provided, That the above period shall be tolled
according to the provisions of section twenty-one of this article.
The period of limitation provided in this section shall not
commence until the improvement to the real property in
question has been occupied or accepted by the owner of the real property, whichever occurs first.
This Court has discussed this statute in depth on three previous occasions which are relevant
to the instant analysis. In both Gibson v. West Virginia Department of Highways, 185
W. Va. 214, 406 S.E.2d 440 (1991), and Shirkey v. Mackey, 184 W. Va. 187, 399 S.E.2d
868 (1990), we addressed the time bar created by this statute of repose. In the third, Stone
v. United Engineering, a Division of Wean, Incorporated, 197 W. Va. 347, 475 S.E.2d 439
(1996), we considered what constitutes an improvement under the statute and found that
the statute did not apply to preclude suit against the owner of property who also designed the
improvement allegedly causing the injury at issue.
The constitutionality of W. Va. Code §55-2-6a was upheld in Gibson v. West
Virginia Department of Highways, 185 W. Va. 214, 406 S.E.2d 440 (1991). Therein, we
explained the purpose and scope of the statute stating:
The purpose of this type of statute of repose is to protect
architects and builders from the increased exposure to liability
as a result of the demise of the privity of contract defense.
Without a statute of repose, a party injured because of a latent
design or defect could sue an architect or builder many years
after a construction project was completed. This could result in
stale claims with a distinct possibility of loss of relevant
evidence and witnesses.
Because architects and builders were the ones primarily
exposed to increased liability when privity of contract was
abolished, we cannot fault our legislature for protecting this
group. Furthermore, our statute is not so narrowly drawn as
some in other jurisdictions. W. Va. Code, 55-2-6a, has a
ten-year limitation and bars recovery in three general areas. The
first relates to damages .for any deficiency in the planning,
design, surveying, observation or supervision of any
construction[.]. The second involves damages arising from .the
actual construction of any improvement to real property [.].
The third area is .for an injury to a person or for bodily injury
or wrongful death arising out of the defective or unsafe
condition of any improvement to real property[.].
Gibson, 185 W. Va. at 220, 406 S.E.2d at 446. Accordingly, we held W. Va. Code,
55-2-6a, limits the time period in which a suit may be filed for deficiencies in the planning,
design, or supervision of construction of an improvement to real property to ten years. Syl.
pt. 1, in part, Id.
Marion relies heavily upon Shirkey v. Mackey, 184 W. Va. 187, 399 S.E.2d
868 (1990), in his argument that the circuit court's order should be affirmed. In Shirkey, this
Court declined to apply the discovery rule to permit a claim arising from an alleged latent
defect in the construction of a home, i.e., construction on improperly compacted organic fill
material resulting in property damage due to settling, to proceed where it was filed twelve
years after construction was complete. In Shirkey, the homeowners allegedly did not
discover the defect until twelve years after the construction was completed and filed suit
shortly thereafter. In rejecting the homeowners' argument that to apply W. Va. Code §55-2-
6a to bar their claim would leave them without remedy, the Court noted that to apply the
discovery rule under the facts of the case would negate the entire purpose of the statute. Shirkey, 184 W. Va. at 159, 399 S.E.2d at 870. Thus, the Court held in the sole syllabus
point that West Virginia Code § 55-2-6a (1983) sets an arbitrary time period after which
no actions, whether contract or tort, may be initiated against architects and builders.
Pre-existing statutes of limitation for both contract and tort actions continue to operate within
this outside limit. Id. Marion argues that this syllabus point clearly indicates that any tort
or contract action related to the construction of a home is barred by W. Va. Code § 55-2-6a
if filed more than ten years after the original construction is complete. The Neals counter
that the statute is not so broad, that the statutory language itself limits its application to
claims for any deficiency in the planning, design, surveying, observation or supervision of
any construction or the actual construction of an improvement and that Shirkey should be
modified to reflect such limitation.
Our review of Shirkey reveals that its sole syllabus point omits a key limitation
on the scope of W. Va. Code §55-2-6a, i.e., the statutory language that only actions seeking
damages for deficiencies in the construction of the improvement at issue, whether its
planning, design or actual construction, are subject to the statutory time bar. The omitted
statutory language directly relates the triggering of the statute to the alleged deficiency at
issue. A cardinal rule of statutory construction is that significance and effect must, if
possible, be given to every section, clause, word or part of the statute. Syllabus Point 3, Meadows v. Wal-Mart Stores, Inc., 207 W. Va. 203, 530 S.E.2d 676 (1999). It has long been
held that [i]n ascertaining legislative intent, effect must be given to each part of a statute
and to the statute as a whole so as to accomplish the general purpose of the legislation. Syl.
Pt. 2, Smith v. State Workermen's Compensation Comm'r, 159 W. Va. 108, 219 S.E.2d 361
(1975). See also, State ex rel. Johnson v. Robinson, 162 W. Va. 579, 582, 251 S.E.2d 505,
508 (1979) (recognizing the presumption that the Legislature intends that every word used
in a statute has a specific purpose and meaning.). This omission in Shirkey, we believe,
contributed to the circuit court's erroneous ruling as it implies the scope of W. Va. Code §
55-2-6a is broader than the intent indicated by the statutory language itself. The omitted
phrase limiting the scope of the statute to actions seeking damages for any deficiency in the
planning, design, surveying, observation or supervision of any construction or the actual
construction of any improvement to real property is significant in that it demonstrates
legislative intent regarding the statutory scope. This phrase links the application of the
statute to the act alleged to be deficient or improper. So, for example, if a home was
constructed and three years after the home was occupied work was performed on the
foundation that is proven to be improper, deficient or inadequate, the statute would not begin
to run from the date of original construction but from the date on which the allegedly
improper, deficient or inadequate work on the foundation was complete. The reason for this
is because it is the second act which is at issue, not the original construction.
Unlike
Shirkey, the instant matter involves allegations that the original builder,
Marion, performed subsequent work on the home
after the original construction had been
completed. There is evidence that defects in the original foundation were repaired, repaired
inadequately, and concealed. However, there is no evidence as to when these repairs and the
alleged walling in occurred. If this foundation work and walling in occurred
after October 1, 1994, W. Va. Code §55-2-6a would not operate to bar the Neals claim because
that is the relevant date - the date on which the improvement at issue was completed. The
subsequent work operates to start W. Va. Code §55-2-6a's time limitation anew for claims
related to that subsequent work. As we stated in
Gibson, the purpose of this statute is to
protect architects and builders from claims asserted many years after construction is
complete.
Gibson, 185 W. Va. at 220, 406 S.E.2d at 446. We also stated in
Stone that the
general purpose of statutes of repose [like W. Va. Code §55-2-6a], including the legislative
intention [is] 'to protect architects, builders and the like
who have completed their jobs and
who have relinquished access and control of the improvements.'
Stone, 197 W. Va. at 355,
475 S.E.2d at 447, quoting,
West End Corp. v. Royals,
450 So.2d 420, 424 (Miss. 1984). In
Stone we recognized that whether something constitutes an improvement for purposes of
W. Va. Code §55-6-2a is a legal determination requiring a common sense approach.
Stone,
197 W. Va. at 357, 475 S.E.2d at 449. Whether the item enhances the value of the real
property and the level of its integration to the real property itself are factors to be considered.
Id. at 358, 475 S.E.2d at 450. Applying a common sense approach, we find that a
subsequent act which modifies or repairs the original design or construction of real property
constitutes an improvement to the original construction for purposes of W. Va. Code §55-
2-6a.
(See footnote 9) The purpose of this statute is not, in our opinion, to protect a builder from claims
arising from actions taken
after the completion of the original construction to conceal or
inadequately repair problems with the original design or construction. So long as those
claims are filed within ten years after the last action taken by the builder on the improvement
at issue, the statutory purpose is fulfilled.
Accordingly, we now hold that West Virginia Code § 55-2-6a (1983) sets an
arbitrary time period after which no actions, whether contract or tort, seeking damages for
any deficiency in the planning, design, surveying, observation or supervision of any
construction or the actual construction of any improvement to real property may be initiated
against architects and builders. This arbitrary time limit begins to run when the builder or
architect relinquishes access and control over the construction or improvement
and the
construction or improvement is (1) occupied or (2) accepted by the owner of the real
property, whichever occurs first. Pre-existing statutes of limitation for both contract and tort
actions continue to operate within this outside limit. To the extent this Court's decisions in
Shirkey v. Mackey, 184 W. Va. 187, 399 S.E.2d 868 (1990), and
Gibson v. West Virginia
Department of Highways, 185 W. Va. 214, 406 S.E.2d 440 (1991), indicate otherwise, they
are hereby modified.
With respect to the Neals' claims arising from alleged deficiencies in the
design or construction of the foundation, the relevant date for purposes of triggering W. Va.
Code §55-2-6a is the last date upon which Marion performed work which altered the original
design or construction of the foundation and such work was accepted by the property
owners, either the Jordans or the Neals. To be clear, this is not a situation where the original
builder or architect relinquished access and control of the construction upon completion of
the original construction.
(See footnote 10) Herein, Marion remained actively involved, including returning
to the home after it was occupied by the owners to allegedly perform alterations to the
original design and/or construction. Should it be determined that the walling in and repairs
to the foundation occurred after October 1, 1994, the Neals' claims relating to the same
would be timely filed under W. Va. Code §55-2-6a. Accordingly, the circuit court's decision
to dismiss the Neals' claims arising from Marion's actions in repairing, altering or walling
in the foundation to conceal its defective nature must be reversed and this matter is remanded
for a determination as to when these actions occurred. If such actions occurred after October
1, 1994, W. Va. Code §55-2-6a does not operate to bar such claims.
The circuit court likewise erred in applying W. Va. Code §55-2-6a to bar the
Neals' claims of fraud, misrepresentation and civil conspiracy arising from Marion's
representations made during the negotiations for the Neals' purchase of the property. There
is a fundamental distinction between defects in the design or construction of the foundation
and affirmative misrepresentations regarding the condition thereof and/or prior repairs
thereto. Where there is a demonstrated reliance upon an affirmative misrepresentation to act
in a certain manner, the damages arise not from the subject matter of the misrepresentation,
here the foundation problems, but from the misrepresentation itself. Stated another way, the
claimed damages arise not from the alleged problems with the foundation but from being
induced to act by a false representation that there were no undisclosed prior repairs to or
problems with the foundation. The alleged misrepresentations and any damages arising
therefrom are not subject to the provisions of W. Va. Code §55-2-6a. This statute governs
only the alleged defects themselves, not claims arising from a representation that there were
no defects or knowingly concealing the extent of the defects or prior repairs. Similarly, to
the extent the Neals' claims for unfair or deceptive acts or practices arise from Marion's
actions and representations during the sale negotiations, the claims are not subject to W. Va.
Code §55-2-6a and the circuit court erred by invoking the same to dismiss those claims.
Accordingly, the circuit court's order relying upon W. Va. Code §55-2-6a to dismiss the
Neals' claims of fraud, misrepresentation, civil conspiracy and unfair or deceptive acts or
practices is reversed and the claims are remanded for further proceedings.
IV.
CONCLUSION
The Circuit Court of Kanawha County's October 30, 2006, order denying
Appellants' Rule 59(e) motion and its October 6, 2006, summary judgment order are
reversed, for the reasons set forth herein, and this matter is remanded for further proceedings.
The only claims at issue in the instant appeal are those asserted against Marion.
Footnote: 3
Appellees Sandy Kessell and Lombardo Realty, n/k/a New Millennium Corporation
were real estate brokers involved in the negotiation and sale of the property.
Footnote: 4
Due to the limited record created below, the factual representations contained herein
are taken from the Neals' complaint and the parties' briefs. The circuit court dismissed the
Neals' claims against Marion based solely upon the date on which construction was complete
in comparison to the date the complaint was filed. Upon remand, the factual representations
contained herein may be subject to dispute by the parties and, if so, should ultimately be
resolved by the trier of fact.
Footnote: 5
The Neals represent in their brief to this Court that the problems were first discovered
in 2002 when they undertook to remodel the home's basement.
Footnote: 6
Included in the complaint were counts for breach of express warranties, breach of
implied warranty of habitability, common law fraud and misrepresentation, statutory unfair
or deceptive acts or practices, fraudulent or negligent inspection and certification, and civil
conspiracy.
Footnote: 7
The Neals represent that Marion did, in fact, perform work pursuant to this
representation after they purchased the home.
Footnote: 8
The appellants articulate four separate, but interrelated, arguments on appeal: 1) the
circuit court erred by applying W. Va. Code §55-2-6a to their fraud and civil conspiracy
claims; 2) the circuit court erred by refusing to acknowledge that the doctrine of equitable
estoppel saves their claims due to the alleged fraudulent concealment and
misrepresentations; 3) the circuit court erred by failing to view facts in light most favorable
to appellants; and 4) the circuit court erred in not setting forth sufficient findings of fact and
conclusions of law. Each, however, involves the circuit court's the application of W. Va.
Code §55-2-6a, which we deem to be the dispositive issue herein.
Footnote: 9
In syllabus point 1 of
Gibson, this Court held: W. Va. Code, 55-2-6a, limits the time
period in which a suit may be filed for deficiencies in the planning, design, or supervision
of construction of an improvement to real property to ten years. This period commences on
the date the improvement is occupied or accepted by the owner of the real property,
whichever occurs first. Implicit in this finding is an understanding that the architect or
builder has relinquished control of the construction or improvement to the owner and has
ceased work thereon.
Footnote: 10
Nor is this a situation where someone other than the original builder performed the
subsequent work. In such an instance, the statute of repose would begin to run as to the
original builder from the date upon which construction was completed and the property
accepted or occupied by the owner.