The Opinion of the Court was delivered PER CURIAM.
JUDGE GARY JOHNSON sitting by temporary assignment.
JUSTICE MAYNARD dissents and reserves the right to file a dissenting opinion.
JUSTICE SCOTT did not participate.
'[A] written contract may be modified or its terms altered by a subsequent valid oral
agreement, and this may be shown in a proper case. . . . ' Syllabus point 2, [in part,]
Jones
v. Kessler, 98 W. Va. 1, 126 S.E. 344 (1925). Syl. Pt. 2, in part, W.L. Thaxton Constr. Co.
v. O.K. Constr. Co., 170 W. Va. 657, 295 S.E.2d 822 (1982)
.
Per Curiam:
This case is before the Court upon the appeal of the Appellant, Ken Lowe
Management Co., from the November 9, 1998, order of the Circuit Court of Grant County,
wherein following a bench trial,See footnote 1
1
judgment was entered in favor of the Appellee, CMC
Enterprises, Inc., in the amount of $42,973 with interest from July 1, 1996. The Appellant
argues that the lower court erred: 1) by failing to apply and construe the contract against the
Appellee, the maker of the contract; 2) in allowing the Appellee to recover for additional
work done on the project in the absence of any written change orders; 3) in making findings
of fact that were inaccurate and in failing to adopt material facts introduced at trial;See footnote 2
2
and 4)
by not allowing interest on the $9,027 credit due to the Appellant prior to granting the
reduction in judgment.
In the Appellee's trial exhibit numbered 18, the lease and supplemental lease
agreement from GSA to the Appellant was not received by the Appellant until May 2, 1996.
The Appellee maintained that the lease referred to apparently was not signed or completed
until after work on the project was completed.
Thus, the Appellee had no knowledge or
benefit of the lease agreement.See footnote 6
6
On April 4, 1996, the Appellee began working on the building in accordance
with the February 29, 1996, contract and the SK-2/96 floor layout.See footnote 7
7
Also on April 4, 1996,
Francis McGafferty of the General Services Administration (GSA) wrote to Ken Lowe,
the president of the Appellant company. In that letter, Mr. McGafferty stated that [u]pon
reading the contract [dated February 29, 1996] I noticed that all work was to be done in
accordance with the attached space layout (existing walls, restrooms, etc.). I would caution
you from proceeding in this manner until I furnish you with a copy of our final floorplan.
According to the letter, the floor plan that was to be used in the remodeling was to be
provided no later than April 17, 1996. According the facsimile information found on the
top of the April 4, 1996, letter from Mr. McGafferty to the Appellant, the letter was not
forwarded to the Appellee until August 28, 1996.
The new floor plans with new specifications that had been prepared by Jim
Bentley of the Social Security Administration and dated April 10, 1996, were received by the
Appellee after April 13, 1996. The new floor plans and specification were materially
different from the old plans. The evidence was uncontradicted that when the new floor plans
were received, the Appellee contacted the Appellant. Subsequently, the Appellee's agents,
Wardney Cosner and Dick Junkins, met with Ken Lowe on two separate occasions.
During
the two meetings, Ken Lowe verbally instructed the Appellee's agents to proceed under the
new floor plans and specifications. The trial court found that Wardney Cosner was told
that GSA, Ken Lowe Management, or Social Security would be responsible for the
difference in the new floor plan from the old [floor plan]. There also were a total of twenty-
eight phone messages or facsimiles from the Appellee to the Appellant and/or GSA and the
Social Security Administration.
On July 1, 1996, the Appellee, via facsimile, sent to the Appellant a ten-page
document which included an invoice totaling $73,762 for additional work not covered by the
original contract.
The Appellant introduced the testimony of Edward Dove, a registered professional engineer with Dove & Associates, Inc., who testified that the standard of the industry was when any additional modifications or changes of any nature to the original contract were necessary, a change order executed by all parties who signed the original construction contract was obtained. Mr. Dove further testified that when additional work is anticipated, work authorizations and/or modifications should be in writing. Mr. Dove also testified that work performed by the Appellee was not in conformance with the contract.See footnote 8 8
Further, Mr. Dove stated that many of the items the Appellee sought recovery for should
have been included in the original contract specifications for the lump sum amount. In
contrast, the Appellee offered evidence that the additional items were recoverable because
a parol modification to the contract, agreed upon
by the parties, had occurred. To that end,
the Appellee offered the testimony of Jeanine S. Bachtel, a registered engineer for
construction and renovation at Frostburg State University, who testified that it was customary
in the industry not to receive written change orders if the contract did not provide for the
same.
The circuit court found that CMC built the building according to GSA plans
(according to the contract)[,] and [t]hat the building now meets GSA specifications. . . .
Further, the lower court found that to permit the Defendant, Ken Lowe Management
Company, to receive $40,000 to $160,000 worth of renovations for $80,195, plus additional
cost options of a rear room of $3,800 and a roof option of $3,500, would be unjust
enrichment.
We use the following standard of review in resolving the assigned error:
when a trial court's answers rest not on plain meaning [of the
contract] but on differential findings by a trier of fact, derived
from extrinsic evidence as to the parties' intent with regard to an
uncertain contractual provision, appellate review proceeds under
the 'clearly erroneous' standard. The same standard pertains
whenever a trial court decides factual matters that are essential
to ascertaining the parties' rights in a particular situation (though
not dependent on the meaning of the contractual terms per se ).
In these types of cases, the issues are ordinarily fact-dominated
rather than law-dominated and, to that extent, the trial court's
resolution of them is entitled to deference.
Fraternal Order of Police, Lodge No. 69 v. City of Fairmont, 196 W.Va. 97, 100, 468 S.E.2d
712, 715 (1996).
In support of its argument,
the Appellant relies upon the well-established
contractual principles that clear and unambiguous contractual provisions should be applied
and not construed. See Syl. Pt. 1, Fraternal Order of Police, 196 W. Va. at 99, 468 S.E.2d
at 714 ('It is not the right or province of a court to alter, pervert or destroy the clear meaning
and intent of the parties as expressed in unambiguous language in their written contract or
to make a new or different contract for them.'). The Appellant's reliance upon these
principles for the resolution of this case, however, completely ignores the fact that the lower
court was not asked to interpret a clear and unambiguous contractual provision
. To the
contrary,
the main issue before the lower court was simply whether the evidence supported
a finding that a parol modification to the original contract occurred. The contract is
completely silent as to any requirement that a change in the terms of the contract need to be
in writing.
This Court has previously held that 'a written contract may be modified or its
terms altered by a subsequent valid oral agreement, and this may be shown in a proper case.
. . . ' Syllabus point 2, [in part,]
Jones v. Kessler, 98 W. Va. 1, 126 S.E. 344 (1925). Syl.
Pt. 2, in part, W.L. Thaxton Constr. Co. v. O.K. Constr. Co., 170 W. Va. 657, 295 S.E.2d 822
(1982)
; see Syl. Pt. 2 of State ex rel. Coral Pools, Inc. v. Knapp, 147 W.Va. 704, 131 S.E.2d
81 (1963) (
"A written contract may be altered or supplemented by a valid parol contract
subsequently made."); see also John W. Lodge Distrib. Co. v. Texaco, Inc., 161 W.Va. 603,
606, 245 S.E.2d 157, 159 (1978); Wilkinson v. Searls, 155 W.Va. 475, 484, 184 S.E.2d 735,
741 (1971); Steinbrecher v. Jones, 151 W.Va. 462, 470, 153 S.E.2d 295, 301 (1967).
In the instant case, the court determined that a parol modification had occurred
and that the Appellee was entitled to recover additional monies based upon said modification
which required additional work not contemplated by the original contract. As we indicated
in W. L. Thaxton Const. Co., the determination of whether there was a parol modification
to a contract is left to the trier of fact, in this case, the lower court. Id. at 660, 295 S.E.2d at
825 (It was for the jury to decide if the written and signed contract had been orally
modified and they did so.). We will not disturb such a finding of fact unless it is clearly
erroneous. See Fraternal Order of Police, 196 W. Va. at 100 , 468 S.E.2d at 715. We
conclude that the circuit court's findings were not clearly erroneous.
As previously stated, factual findings made by the trial are given great
deference by this Court and will not be overturned unless they are clearly erroneous. See
Fraternal Order of Police, 196 W.Va. at 100 , 468 S.E.2d at 715. In the instant case,
the fact
that the trial court found that certain modifications had been made pursuant to written change
orders, does not negate the fact that a parol modification was agreed to by the parties.
Further, regarding the trial court's finding that the building met GSA specifications, it was
certainly within the trial court's purview to decide what evidence was credible and what
evidence was not credible. That factual finding apparently
reflects that the trial court did not
find the Appellant's evidence credible on this issue. From a review of the record, we find
that the factual findings reflect the trial court's thoughtful review of the evidence presented
and are not clearly erroneous.
We generally review decisions involving prejudgment interest under an abuse
of discretion standard. See Gribben v. Kirk, 195 W. Va. 488, 500, 466 S.E.2d 147, 159
(1995).
West Virginia Code § 56-6-31 (1997) provides, in pertinent part, that [e]xcept
where it is otherwise provided by law, every judgment or decree for the payment of money
entered by any court of this State shall bear interest from the date thereof . . . . Id. West
Virginia Code § 56-6-27 (1997), however, is the general authority for awarding prejudgment
interest in a contract action. See First Nat'l Bank of Bluefield v. Clark, 191 W. Va. 623,
625, 447 S.E.2d 558, 560 (1994). That provision provides
The jury, in any action founded on contract, may allow
interest on the principal due, or any part thereof, and in all cases
they shall find the aggregate of principal and interest due at the
time of the trial, after allowing all proper credits, payments and
set-offs; and judgment shall be entered for such aggregate with
interest from the date of the verdict.
W. Va. Code § 56-6-27.
In the instant case, it is evident from the circuit court's order that the Appellant
was not awarded any judgment on its counterclaim.See footnote 10
10
Rather, recognizing that the evidence
supported the Appellant's contention that it was entitled to a $9,027 credit, the circuit court
correctly deducted that credit before interest was calculated on the balance due the Appellee.
Based on the foregoing, the judgment of the Circuit Court of Grant Count,
West Virginia, is hereby affirmed.
Footnote: 1 1While the entire original record was designated by the Appellant for purposes of this appeal, the transcript of the bench trial proceedings was not part of the record.
Footnote: 2 2The second and third assignments of error are largely the same. Consequently, we address these issues as one.
Footnote: 3 3 The Appellee had no contractual obligations with the General Services Administration (GSA) or the Social Security Administration .
Footnote: 4 4The contract documentation dated November 13, 1995, was a solicitation or offer between the Appellant and General Services Administration.
Footnote: 5 5 The Appellant had not yet entered into a lease with the Social Security Administration for the remodeled space at the time the contract was made.
Footnote: 6 6 The actual lease agreement superseded the solicitation or offer dated November 13, 1995.
Footnote: 7 7 The work was finished on or about June 1, 1996.
Footnote: 8 8Francis McCafferty, contracting officer with GSA, corroborated the testimony that the Appellee's work was not performed in accordance with the contract. According to the Appellant, a letter dated April 4, 1996, from Mr. McCafferty to the Appellant, proves that the building did not meet GSA specifications and that GSA was due a credit of $14,309 as there were items to be included in the original contract price which were not installed.
Footnote: 9 9The actual finding made by the circuit court was:
That throughout the course of the project, on two occasions, April 23, 1996, and May 7, 1996, CMC Enterprise Inc. provided to Ken Lowe Management Company written confirmation of additional work requested by CMC to include overtime and security system which indicated a course of dealing between the parties for written change orders and additional expenditures of funds to be approved in writing, which Ken Lowe Management Company did approve.
Footnote: 10 10The Appellant was seeking $100,000 in damages for fraud and misrepresentation in its counterclaim, as well as the $9,027 credit, plus interest and costs.