Davis, Chief Justice, concurring, in part, and dissenting, in part:
Although the majority opinion
found that completion of the project by Big Sandy rendered ACT's complaint
moot, the majority nevertheless proceeded to address the merits of the issues
raised. In so doing, the majority opinion ruled that ACT had standing to file
a complaint against Big Sandy. For the reasons set out below, I dissent from
the majority opinion's ruling on the standing issue.
Pursuant to W. Va. Code
§ 24-2-11(a) (1983) (Repl. Vol. 2001), the PSC is required to provide
notice to the public of a request for a certificate of convenience and necessity.
(See footnote 1)
The notice requirement is intended to allow any interested party to attend
a scheduled hearing to voice any concerns regarding a third party's request
for a certificate of convenience and necessity. The record revealed that the
PSC required Big Sandy to make two legal publications advising the
public of the pendency of its request for a certificate of convenience and
necessity. As a result of the legal publications, two parties intervened and
were given an opportunity by the PSC to voice their concerns. ACT did
not attempt to intervene while the PSC was considering Big Sandy's request
for a certificate of convenience and necessity. Had ACT so intervened
and objected to the PSC's ruling, ACT could then have appealed an unfavorable
ruling. However, rather than intervening as authorized by W. Va. Code §
24-2-11(a), ACT waited nearly six months after the PSC had granted
the certificate of convenience and necessity to raise its objections. At that
point, ACT filed a complaint seeking to revoke the certificate of convenience
and necessity. ACT relied upon W. Va. Code
§ 24-4-6 (1923) (Repl. Vol. 2001) in order to file its complaint. W.
Va. Code § 24-4-6 permits a party to enforce compliance with the statutory,
regulatory, and other requirements that are imposed upon an entity that obtains
a certificate of convenience and necessity.
(See footnote 2) This statute, as conceded
to by the majority opinion, cannot be used to revoke the issuance of a certificate
of convenience and necessity. A party seeking to revoke the issuance of a
certificate of convenience and necessity must appeal the order granting such
certificate. The complaint filed by ACT
pursuant to W. Va. Code § 24-4-6 expressly sought the following relief
from the PSC: It is simply illogical for
the majority opinion to conclude that ACT was not seeking to revoke the certificate
of convenience and necessity issued to Big Sandy. ACT was crystal clear in
its complaint. It requested the certificate of convenience and necessity be
revoked, and that no new certificate of convenience
and necessity be issued until Big Sandy met the requirements imposed by ACT.
I submit that the majority opinion is a calculated distortion of the record
and is imposing greater, nonstatutory, duties upon the PSC. These new duties,
as outlined by the majority opinion, permit any future entities
(See footnote 3)
to have uncontrollable power in challenging the issuance of a certificate
of convenience and necessity. It is unfortunate that the majority opinion
has resorted to such legislative authorship rather than staying within the
confines of our constitutional role as the judicial branch of government. For the reasons stated,
I concur, in part, and dissent, in part, from the majority opinion. I am authorized
to state that Justice Maynard joins me in this opinion and reserves the right
to author a separate opinion.
Notice shall be given by
publication which shall state that a formal hearing may be waived in the absence
of protest, made within thirty days, to the application. The notice shall
be published as a Class I legal advertisement in compliance with the provisions
of article three, [§§ 59-3-1 et seq.], chapter fifty-nine of this
code.
In this proceeding, the Affiliated
Construction Trades Foundation (hereinafter referred to as ACT)
challenged a ruling by the Public Service Commission (hereinafter referred
to as PSC), which concluded that ACT had no standing to litigate
issues involving a certificate of convenience and necessity that was issued
to Big Sandy Peaker Plant (hereinafter referred to as Big Sandy).
The majority opinion determined that granting relief to ACT was impossible
because the project complained of had been completed. Therefore, the majority
opinion properly affirmed the PSC's dismissal of ACT's complaint. With this
part of the majority opinion, I concur.
The PSC maintained that ACT
sought to revoke the certificate of convenience and necessity issued to Big
Sandy. Consequently, the PSC argued, ACT had no standing to file a complaint
in the matter. To justify addressing this case on the merits, the majority opinion
stated that [i]f ACT sought only the revocation of the permit, the finality
argument might be considered more viable. In other words, the majority
opinion agreed that ACT had no standing to revoke the certificate of convenience
and necessity. However, to support its finding that ACT did have standing in
this case, the majority opinion disingenuously concluded that ACT did not actually
seek to revoke the certificate of convenience and necessity. Unfortunately,
the record fails to support the majority's conclusion. In fact, the record clearly
reveals that ACT indeed sought to revoke the certificate of convenience and
necessity issued to Big Sandy.
i.
That the Commission revoke the Certificate of Convenience and Necessity
it issued on June 23, 2000 concerning [Big Sandy's] facility and Order all
construction and other work to cease.
ii.
That the Commission issue an Order revoking the waiver of the requirement
to provide information listed in paragraphs 5 through 9 of Form 5 of the Commission's
Tariff Rules and the Information required by Rule 42 of the Tariff and Ordering
[Big Sandy] to provide said information.
iii.
That the Commission investigate the circumstances under which [Big Sandy]
applied for and obtained said Certificate.
iv.
That the Commission not issue a new Certificate of Convenience and
Necessity for said facility unless and until it determines that [Big Sandy]
has met its burden and complies with all aspects of West Virginia Code Section
24-2-11 including its burden to demonstrate an improved economy in light of
the impact on the economic health of the community and the State through the
use of revenue bonds and a PILOT plan.
v.
That the Commission Order [Big Sandy] to meet its obligations to the economic
health of the State and the Community through the exclusive hiring of local
workers and contractors for the construction and operation of the facility.
(Emphasis added).
In its opinion, the majority
states that ACT had standing in this case because ACT was not seeking to revoke
the certificate of convenience and necessity issued by the PSC to Big Sandy.
However, as indicated above in paragraph i, ACT specifically requested
[t]hat the Commission revoke the Certificate of Convenience and
Necessity it issued on June 23, 2000 concerning [Big Sandy's] facility[.]
(Emphasis added). Moreover, in paragraph iv, ACT specifically requested
[t]hat the Commission not issue a new Certificate of Convenience
and Necessity for said facility unless and until it determines that [Big Sandy]
has met its burden and complies with all aspects of West Virginia Code Section
24-2-11[.] (Emphasis added).
Footnote: 1
Footnote: 2
Any
person, firm, association of persons, corporation, municipality or county, complaining
of anything done or omitted to be done by any public utility subject to this
chapter, in contravention of the provisions thereof, or any duty owing by it
under the provisions of this chapter, may present to the commission a petition
which shall succinctly state all the facts. Whereupon, if there shall appear
to be any reasonable ground to investigate such complaint, a statement of the
charges thus made shall be forwarded by the commission to such public utility,
which shall be called upon to satisfy such complaint or to answer to the same
in writing within a reasonable time to be specified by the commission. If such
public utility within the time specified shall make reparation for the injury
alleged to have been done, or correct the practice complained of and obey the
law and discharge its duties in the premises, then it shall be relieved of liability
to the complainant for the particular violation of the law or duty complained
of. If such public utility shall not satisfy the complainant within the time
specified, it shall be the duty of the commission to investigate the same in
such manner and by such means as it shall deem proper.
Footnote: 3